During a project's initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk's likelihood and impact with the risk manager. What should the risk manager do?
Correct Answer: D
The probability-impact matrix is a standard tool for qualitative risk analysis, as recommended by PMI: "A probability and impact matrix is used to prioritize identified risks for further analysis or action by combining their probability of occurrence and impact on project objectives." - PMBOK Guide, 6th Edition, Section 11.3 This ensures the most critical risks are prioritized for response planning. References: PMBOK Guide, 6th Edition, Section 11.3