Valid PMI-RMP Dumps shared by ExamDiscuss.com for Helping Passing PMI-RMP Exam! ExamDiscuss.com now offer the newest PMI-RMP exam dumps, the ExamDiscuss.com PMI-RMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-RMP dumps with Test Engine here:
A risk manager has been assigned to prepare a risk management plan for a new project. Which factor should the risk manager prioritize when tailoring the risk management processes for the new project?
Correct Answer: B
Tailoring risk management processes is mainly based on the size and duration (complexity) of the project. The PMBOK Guide confirms: " The size, complexity, and duration of the project are primary considerations when tailoring risk management activities. Larger or longer projects require more rigorous processes. " - PMBOK Guide, 6th Edition, Section 11.1 References: PMBOK Guide, 6th Edition, Section 11.1