As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.
What is the total contingency budget that should be created?
Correct Answer: B
In risk management, to calculate the contingency budget for risks, we use the Expected Monetary Value (EMV) formula: EMV=Probability of Risk×Impact of Risk\text{EMV} = \text{Probability of Risk} \times
\text{Impact of Risk}EMV=Probability of Risk×Impact of Risk
For Risk A:
Probability: 40% or 0.40
Impact: US$100,000\text{EMV of Risk A} = 0.40 \times 100,000 = US$40,000 For Risk B:
Probability: 60% or 0.60
Impact: US$20,000\text{EMV of Risk B} = 0.60 \times 20,000 = US$12,000
Total contingency budget = EMV of Risk A + EMV of Risk B
40,000 + 12,000 = US$52,000
Thus, the total contingency budget required for both risks is US$52,000. This approach follows PMI's risk management guidelines, specifically under the " Quantitative Risk Analysis " process. This process focuses on determining numerical probabilities and monetary impacts to compute the expected financial impact of identified risks.