<< Prev Question Next Question >>

Question 143/171

What provides information regarding the ways people, teams, and organizational units behave?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (171q)
Question 1: A project lifecycle is defined as:...
Question 2: Which of the following is an output of the Monitor and Contr...
Question 3: Perform Integrated Change Control is the process of:...
Question 4: Status of deliverables, implementation status for change req...
Question 5: How should a stakeholder who is classified as high power and...
Question 6: An input to the Create WBS process is a:...
Question 7: The process of identifying the stakeholders' information nee...
Question 8: When a permitting agency takes longer than planned to issue ...
Question 9: What scenario describes when a project must be created due t...
Question 10: Design of experiments (DOE) should be used during which of t...
Question 11: A new project manager wishes to recommend creating a project...
Question 12: What should the project manager use to evaluate the politics...
Question 13: Which baselines make up the performance measurement baseline...
Question 14: A project manager needs to request outside support for a sta...
Question 15: Which of the following is a means of reaching a group decisi...
Question 16: How is the schedule variance calculated using the earned val...
Question 17: An imposed date for completion of the project by the custome...
Question 18: Which of the following processes audits the quality requirem...
Question 19: The diagram below is an example of a: (Exhibit)...
Question 20: In which type of contract are the performance targets establ...
Question 21: The process of identifying and documenting project roles, re...
Question 22: In which domain of project management would a Pareto chart p...
Question 23: The Perform Integrated Change Control process occurs in whic...
Question 24: Project management processes ensure the:...
Question 25: A stakeholder is reading project documents given by the proj...
Question 26: The three processes of Project Cost Management are:...
Question 27: At which stage of team development do members begin to work ...
Question 28: Exhibit A is an example of which of the following types of S...
Question 29: Which process requires implementation of approved changes?...
Question 30: Which schedule compression technique has phases or activitie...
Question 31: The Project Human Resource Management process that involves ...
Question 32: Which input to the Identify Stakeholders process provides in...
Question 33: Which is an enterprise environmental factor?...
Question 34: The following is a network diagram for a project. (Exhibit) ...
Question 35: Projects, programs, subsidiary portfolios, and operations ma...
Question 36: Which characteristics do effective project managers possess?...
Question 37: What is an example of an emerging trend in procurement manag...
Question 38: Which of the following is a complete set of indexed contract...
Question 39: Which action should a project manager take to ensure that th...
Question 40: To which knowledge area does the Collect Requirements proces...
Question 41: To please the customer, a project team member delivers a req...
Question 42: The Perform Quality Assurance process occurs in which Proces...
Question 43: What tool or technique uses an algorithm or statistical rela...
Question 44: A full-time project manager with low to moderate authority a...
Question 45: During which process would stakeholders provide formal accep...
Question 46: The degree of uncertainty an entity is willing to take on in...
Question 47: An input to the Estimate Activity Resources process is:...
Question 48: A project manager of a civil construction project is trying ...
Question 49: On what is project baseline development established?...
Question 50: Which of the following tasks focuses on decomposing work pac...
Question 51: Scope, schedule, and cost parameters are integrated in the:...
Question 52: Fast tracking is a schedule compression technique used to sh...
Question 53: In project management, a temporary project can be:...
Question 54: What is the term assigned to products or services having the...
Question 55: An input to Develop Project Charter is a/an:...
Question 56: Which project risk listed in the table below is most likely ...
Question 57: Which is the correct formula for calculating expected activi...
Question 58: When an activity cannot be estimated with a reasonable degre...
Question 59: Which of the following is a tool and technique used in the D...
Question 60: Which kind of communication should the project manager use w...
Question 61: Which is the appropriate tool to identify the possible corre...
Question 62: Which document defines how a project is executed, monitored ...
Question 63: During a project's execution phase, the project manager revi...
Question 64: Requirements documentation, requirements management plan, an...
Question 65: The project budget is set at $150,000. The project duration ...
Question 66: An output of the Plan Quality Management process is:...
Question 67: What does a CPI value greater than 1.0 indicate?...
Question 68: What is an objective of the Develop Project Team process?...
Question 69: Which earned value management (EVM) metric is a measure of t...
Question 70: What is the responsibility of the project manager and the fu...
Question 71: The degree of uncertainty an entity is willing to take on in...
Question 72: When does Monitor and Control Risks occur?...
Question 73: What is both an input and output of the Control Quality proc...
Question 74: A project lifecycle is defined as:...
Question 75: The staffing management plan is part of the:...
Question 76: Which tool or technique is used to develop a project charter...
Question 77: Risk responses reflect an organization's perceived balance b...
Question 78: Which type of analysis would be used for the Plan Quality pr...
Question 79: In a large organization, with projects of different types an...
Question 80: At what stages of a project should the Identify Stakeholders...
Question 81: What are the five Project Management Process Groups?...
Question 82: Conditions that are not under the control of the project tea...
Question 83: Which tasks should a project manager accomplish in order to ...
Question 84: If a project manager effectively manages project knowledge, ...
Question 85: The definition of when and how often the risk management pro...
Question 86: A change log for communications can be used to communicate t...
2 commentQuestion 87: A project manager is working on project cost management. The...
Question 88: During the execution phase of a project a defect is found. T...
Question 89: Ensuring that both parties meet contractual obligations and ...
Question 90: The cost benefit analysis tool is used for creating:...
Question 91: Which of the following is a tool and technique used to monit...
1 commentQuestion 92: DRAG DROP Match each tool or technique to its corresponding ...
Question 93: When an activity cannot be estimated with a reasonable degre...
Question 94: If the most likely duration of an activity is five weeks, th...
Question 95: While processes in the Planning Process Group seek to collec...
Question 96: Inputs to the Plan Schedule Management process include:...
Question 97: A project manager is writing a document that obligates the s...
Question 98: What should a project manager do to prepare a risk managemen...
Question 99: Soft logic is also known as what type of dependency?...
Question 100: Which statement about identification and engagement of stake...
2 commentQuestion 101: Deciding the phases of project life cycle would be considere...
Question 102: Which of the following can a project manager use to represen...
Question 103: Which type of analysis is used to examine project results th...
Question 104: The process for performing variance analysis may vary, depen...
Question 105: A project manager is working on an estimate. The project tea...
Question 106: While implementing an approved change, a critical defect was...
Question 107: Which of the following tools or techniques is used for Estim...
Question 108: The output that defines an approach to increase the support ...
Question 109: Which process involves developing an approximation of the mo...
Question 110: Lessons learned documentation is gathered during which of th...
Question 111: The most appropriate project life cycle model for an environ...
Question 112: Which Plan Schedule Management tool or technique may involve...
Question 113: Fast tracking is a schedule compression technique used to sh...
Question 114: Which type of elaboration allows a project management team t...
Question 115: Quality metrics are an output of which process?...
Question 116: The definition of when and how often the risk management pro...
Question 117: Which tool should a project manager consider to deal with mu...
Question 118: Which input to the Identify Stakeholders process provides in...
Question 119: An input of the Plan Procurement Management process is:...
Question 120: Which key interpersonal skill of a project manager is define...
Question 121: What are the project management processes associated with pr...
Question 122: Risk categorization is a tool or technique used in which pro...
Question 123: Which type of contract gives both the seller and the buyer f...
Question 124: A project manager can choose from several techniques to reso...
Question 125: After defining activities in project schedule management, wh...
Question 126: Which conflict resolution technique searches for solutions t...
Question 127: Updates to organizational process assets such as procurement...
Question 128: If a project manager effectively manages project knowledge, ...
Question 129: Which schedule development technique modifies the project sc...
Question 130: Which tool or technique measures performance of the project ...
Question 131: Which key interpersonal skill of a project manager is define...
Question 132: At the start of a typical project life cycle, costs are:...
Question 133: Analytical techniques are a tool and technique of which proc...
Question 134: A car company authorized a project to build more fuel-effici...
Question 135: Which two processes should be used to influence costs in the...
Question 136: When managing costs in an agile environment, what should a p...
Question 137: Project managers play a key role in performing integration o...
Question 138: What cost control technique is used to compare actual projec...
Question 139: The project manager needs to manage a critical issue immedia...
Question 140: Which Control Stakeholder Engagement tool or technique allow...
Question 141: Tools and techniques used for Plan Communications include th...
Question 142: In an agile or adaptive environment, when should risk be mon...
Question 143: What provides information regarding the ways people, teams, ...
Question 144: Configuration identification, configuration status accountin...
Question 145: According to the PMI Talent Triangle, leadership skills rela...
Question 146: Which statement is related to the project manager's sphere o...
Question 147: The scope management plan is a subsidiary of which project d...
Question 148: Which of the following is an input to the Direct and Manage ...
Question 149: Plan Schedule Management is a process in which Knowledge Are...
Question 150: A tool and technique used during the Perform Qualitative Ris...
Question 151: Which of the following are examples of interactive communica...
Question 152: An effective technique for resolving conflict that incorpora...
Question 153: Which of the following is an example of a risk symptom?...
Question 154: Which group is formally chartered and responsible for review...
Question 155: Which process involves aggregating the estimated costs of th...
Question 156: In the Define Activities process, the schedule management pl...
Question 157: What is the name of the statistical method that helps identi...
Question 158: A project manager needs to deliver the project 2 weeks befor...
Question 159: Which written document helps monitor who is responsible for ...
Question 160: Which tool or technique is used in the Develop Project Manag...
Question 161: Which Knowledge Area is concerned with the processes require...
Question 162: The number of potential communication channels for a project...
Question 163: Which type of probability distribution is used to represent ...
Question 164: As the project progresses, which of the following is routine...
Question 165: Change requests are processed for review and disposition acc...
Question 166: Which tool or technique is an examination of industry and sp...
Question 167: Outputs of the Control Communications process include:...
Question 168: Decomposition, rolling wave planning, and templates are all ...
Question 169: Project management processes are:...
Question 170: Which is an example of Administer Procurements?...
Question 171: Which type of dependency is established based on knowledge o...