What cost control technique is used to compare actual project performance to planned or expected performance?
Correct Answer: D
Section: Volume C Explanation: 5.6.2.1 Variance Analysis Variance analysis is a technique for determining the cause and degree of difference between the baseline and actual performance. Project performance measurements are used to assess the magnitude of variation from the original scope baseline. Important aspects of project scope control include determining the cause and degree of variance relative to the scope baseline (Section 5.4.3.1) and deciding whether corrective or preventive action is required.