Valid 1z0-1057-22 Dumps shared by ExamDiscuss.com for Helping Passing 1z0-1057-22 Exam! ExamDiscuss.com now offer the newest 1z0-1057-22 exam dumps, the ExamDiscuss.com 1z0-1057-22 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1z0-1057-22 dumps with Test Engine here:
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)
Correct Answer: A
Reference https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-control-configuration-manage-financial-and-project-plan-types.html#OAPFM79055 Topic - Project Date Cascade Options Use the Cascade option choice list to determine whether your changes to project dates cascade to tasks. Use the Basic Information region on the Edit Project Template page to select one of the following options: Do not cascade project date changes to tasks: Both start and finish dates are editable. However, you must ensure the following: The project start date is not later than the earliest task date. The project finish date is not earlier than the latest task date. Cascade project start date change to affected tasks: You can edit only the project start date. Cascade project finish date change to affected tasks: You can edit only the project finish date. Do not cascade project date changes to tasks is the default value. You must select the cascade option each time you change the project dates, as your selection isn't saved for future date changes. If you select to roll up planned dates for tasks or are using an external application for scheduling, then you can't modify the project start or finish dates.