Valid 1z0-1057-22 Dumps shared by ExamDiscuss.com for Helping Passing 1z0-1057-22 Exam! ExamDiscuss.com now offer the newest 1z0-1057-22 exam dumps, the ExamDiscuss.com 1z0-1057-22 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1z0-1057-22 dumps with Test Engine here:
You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting milestone tasks. (Choose three.)
Correct Answer: C,D,E
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapex/define-project-management-configuration.html#OAPEX1357147 Topic - Microsoft Project Prevalidation: Explained The following table describes Prevalidation rules for tasks and resource assignments. Level Rule Lowest-level tasks One labor and multiple expense resources are allowed for a lowest-level task. Remove other resources. Summary tasks Only one labor resource with zero allocation is allowed for a summary task. Remove all other resources. Milestone tasks No subtasks are allowed under milestone tasks. Milestones must be lowest-level tasks. Milestone tasks Milestone tasks must have zero duration. Milestone tasks Only one labor resource, with zero effort, is allowed for a milestone task. Remove all other resources. When exporting milestone tasks, ensure that the tasks: Are lowest-levels task with zero duration, that is, the same start and finish dates. Have only one labor resource assignment with zero effort. Have percent work complete values of 0 or 100 percent. Any other values are set to zero before export.