Valid 1z0-1057-22 Dumps shared by ExamDiscuss.com for Helping Passing 1z0-1057-22 Exam! ExamDiscuss.com now offer the newest 1z0-1057-22 exam dumps, the ExamDiscuss.com 1z0-1057-22 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1z0-1057-22 dumps with Test Engine here:
You have defined two expenditure types, but they are not available for selection when you enter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)
Correct Answer: A
Ref: Implementing-Project-Financial-Management-and-Grants-Management.pdf (19A Part # F11256-01) Chapter 3 - Define Project Organizations Topic - Set Assignments and Project Data - How They Work Together (Page 29) Business Unit as Set Determinant Business units enable you to control and report on financial transactions, usually for specific geographical entities within the enterprise. For project management purposes, assign the Project Accounting business function to the business unit. Business unit is a set determinant for the project-related reference data objects described in the following table. Ref Data Object Entities Project Accounting Definition Project Types Project Rates Project rate schedules Project Unit as Set Determinant Use project units to enforce consistent project management practices across your enterprise. Project unit is a set determinant for the reference data objects described in the following table. Ref Data Object Entities Project Definition Class codes, financial plan types, project plan types and project roles Project Transaction Types Expenditure types and work types You can only select class codes, plan types, roles, expenditure types and work types that are assigned to the same set as the project unit. To enable expenditure types and work types for use on projects owned by a project unit, assign the set associated with the Project Transaction Types reference data object to those entities