Valid Project-Planning-Design Dumps shared by EduDump.com for Helping Passing Project-Planning-Design Exam! EduDump.com now offer the newest Project-Planning-Design exam dumps, the EduDump.com Project-Planning-Design exam questions have been updated and answers have been corrected get the newest EduDump.com Project-Planning-Design dumps with Test Engine here:
Which of the following is the most appropriate action for the architect to take in preparing a construction cost estimate for an owner after completing the schematic design phase?
Correct Answer: A
Comprehensive and Detailed Explanation From Exact Extract: Contingency allowances should be larger during the earlier phases (such as schematic design) due to greater unknowns and potential design changes. As the design progresses and more details are defined, contingency can be reduced. Varying contingency based on owner funds (B) is inappropriate. Contingency during construction administration (C) is typically lower. Doubling contingency for CM use (D) is not standard practice. References: ARE 5.0 PPD - Project Costs and Budgeting The Architect's Handbook of Professional Practice, 15th Edition - Cost Estimating