An architect has just received client approval of the Schematic Design documents for a three-story, outpatient medical clinic. The clinic is located within a mixed-use development governed by a City-approved Planned Development (PD) document. The medical clinic design utilizes standardized departmental layouts and includes outpatient clinics, as well as treatment spaces, administrative spaces and public/lobby spaces.
The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop.
The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The building entrance faces northwest, convenient to the parking but not visible from the highway.
The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would include a second building (2 story, 80,000 BGSF) and/or a parking deck.
Other considerations for the project include:
* Protected tree requirements are defined in the PD document.
* Easy pedestrian access must be provided from Sycamore Boulevard.
* All required parking for the clinic must be accommodated on site.
* Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF).
* Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes.
* All service equipment needs to be screened; see PD document for restrictions.
* Signage opportunities are important to the client.
* Acoustical privacy is a concern of the healthcare system.
The following resources are available for your reference:
* Drawings, including a perspective, plans, and exterior elevations
* Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion)
* Exterior Material Cost Comparisons
* Planned Development Document
* IBC Excerpts, showing relevant code sections
* ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design Pink granite is specified as an exterior material for the outpatient medical clinic. The owner directs the architect to propose alternate, less expensive materials to be used in lieu of the pink granite.
Which of the following materials should be considered to reduce cost? Check the two that apply.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (50q)
Question 1: Click on the shading device illustration that most effective...
Question 2: According to model codes, wind pressure can be positive on t...
Question 3: An elementary school requires a renovation, selective demoli...
Question 4: An architect has just received client approval of the Schema...
Question 5: Which of the following are characteristics of heavy-timber c...
Question 6: An elementary school requires a renovation, selective demoli...
Question 7: A recital hall requires a clear span of 75 feet. Special con...
Question 8: A client asks that a lighting system be designed using the i...
Question 9: A one-story residence in a dry climate with cold winter nigh...
Question 10: Refer to the exhibit (louvered sunscreen cantilevered with b...
Question 11: Which of the following is the most appropriate action for th...
Question 12: Which strategy enhances passive solar residential design in ...
Question 13: To reduce embodied energy in a 500-unit redevelopment, the a...
Question 14: Examples of regulatory controls include which of the followi...
Question 15: A midrise concrete frame structure originally designed for a...
Question 16: An architect is designing an office building on an infill lo...
Question 17: Click in the structural bay of the elevation that is the mos...
Question 18: A multistory warehouse is to be converted into a high-tech o...
Question 19: If evaluating on a life-cycle basis, which of the following ...
Question 20: (Exhibit) A new, sprinklered, mid-rise office building of Ty...
Question 21: Which of the following strategies is most appropriate for a ...
Question 22: The design of a large, one-story building to be used for the...
Question 23: A site has been engineered with a 1:20 grade. Which of the f...
Question 24: When laying out access routes and parking lots for an office...
Question 25: An owner requests full height, motorized solar shades for th...
Question 26: Which of the following roofing types is the most appropriate...
Question 27: An architect's client is focused on lighting energy savings ...
Question 28: An architect has just received client approval of the Schema...
Question 29: An architect has just received client approval of the Schema...
Question 30: An elementary school requires a renovation, selective demoli...
Question 31: Which of the following need to be considered to enhance the ...
Question 32: (Exhibit) Refer to the exhibit (stair connecting four storie...
Question 33: A new gallery is being built and requires shading elements t...
Question 34: An architect is commissioned to design a lodge in a location...
Question 35: Which plumbing criteria will offer a flexible design for a 1...
Question 36: An elementary school requires a renovation, selective demoli...
Question 37: An architect is designing a multistory student housing proje...
Question 38: Comprehensive recycling of materials from building demolitio...
Question 39: An architect is developing a master plan for a small area of...
Question 40: Which of the following is the most effective way to reduce n...
Question 41: During design development of a new college laboratory facili...
Question 42: An architect has just received client approval of the Schema...
Question 43: (Exhibit) Refer to the exhibit (photo showing diagonal crack...
Question 44: A proposed six-story commercial building will have a basemen...
Question 45: The architect's greatest contribution to good seismic design...
Question 46: An architect is selecting a mechanical system for the first ...
Question 47: An architect is working with a developer to determine which ...
Question 48: An architect has just received client approval of the Schema...
Question 49: An existing building containing the maximum allowable area m...
Question 50: Refer to the exhibit (residential floor plan with three outl...