Your development team is working through their bug backlog and tracking their progress on the Bugs dashboard. You look at the active bugs by assignment report and notice that the average size of your team members' bands for active bugs is increasing over time. You need to identify the issues blocking the team's progress toward resolving and closing bugs. Which issue should you investigate?
Correct Answer: D
Explanation/Reference: Bug progress indicators include: * The band for active Bugs is becoming wider. Questions to ask: Are team members being reallocated to other, non-priority tasks? Are other issues blocking the team's ability to resolve and fix Bugs? Reference: Bugs dashboard