You are using Microsoft Test Manager (MTM). You are using the Microsoft Solution Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement process template. Your Team Foundation Server (TFS) 2012 server is configured to support reporting.
You are tracking testing progress for the requirements in the iteration.
You need to identify the report that provides the following:
Verify that all requirements are covered by test cases.

Determine the number of hours of work remaining for each requirement.

Determine the percentage of completion for each requirement.

Determine the number of bugs for each requirement.

Which report should you use?
Correct Answer: A
Explanation/Reference:
The Requirements Overview report lists all requirements, filtered by area and iteration and in order of importance.
You can use this report to answer the following questions:
How much work does each Requirement require?
How much work has the team completed for each Requirement?
Are the tests for each Requirement passing?
How many active bugs does each Requirement have?
Reference: Requirements Overview Report (CMMI)