You are using Microsoft Test Manager (MTM). You are using the Microsoft Solution Framework (MSF) for Agile Software Development process template. SharePoint integration and reporting are enabled.
You want to assess your team's testing effort.
To do this, you need to:
Identify how much testing has the team completed,

Determine whether the team is likely to finish the testing on time,

Identify how many tests have passed, failed, or blocked, and

Identify how many tests are left to be run.

What should you do?
Correct Answer: B
Explanation/Reference:
After the team creates test plans and starts to run tests by using Microsoft Test Manager, you can use the Test Plan Progress report to track the team's progress in testing the product.
You can use this report to answer the following questions:
How much testing has the team completed?
Is the team likely to finish the testing on time?
How many tests are left to be run?
How many tests are passing?
How many tests are failing?
How many tests are blocked?
Reference: Test Plan Progress Report