What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?
Correct Answer: C
Explanation/Reference: Explanation: The risk management plan defines how risks will be identified, analyzed, responded to, and then monitored and controlled regardless of the structure of the organization. AnswerD is incorrect. The human resources management plan does define how risks will be analyzed. Answer: B is incorrect. The staffing management plan does define how risks will be analyzed. Answer: A is incorrect. The risk analysis plan does define how risks will be analyzed.