Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid configuration management activities except for which one?
Correct Answer: D
Explanation/Reference: Explanation: Configuration item cost is not a valid activity for configuration management. Cost changes are managed by the cost change control system; configuration management is concerned with changes to the features and functions of the project deliverables.