Elizabeth is a project manager for her organization and she finds risk management to be very difficult for her to manage. She asks you, a lead project manager, at what stage in the project will risk management become easier. What answer best resolves the difficulty of risk management practices and the effort required?
Correct Answer: D
Explanation/Reference: Explanation: According to the PMBOK, "Like many things in project management, the more it is done the easier the practice becomes." AnswerB is incorrect. This answer is not the best choice for the project. AnswerA is incorrect. Risk management likely becomes more difficult in project execution that in other stages of the project. AnswerC is incorrect. Risk management does become easier the more often it is done.