Valid COBIT-2019 Dumps shared by ExamDiscuss.com for Helping Passing COBIT-2019 Exam! ExamDiscuss.com now offer the newest COBIT-2019 exam dumps, the ExamDiscuss.com COBIT-2019 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com COBIT-2019 dumps with Test Engine here:
Which of the following components is important to update in a COBIT RACI chart to align with the enterprise's context, priorities and preferred terminology?
Correct Answer: B
Explanation The enterprise roles and organizational structures component is important to update in a COBIT RACI chart to align with the enterprise's context, priorities and preferred terminology. A RACI chart is a tool that assigns different levels of responsibility, accountability, consultation, and information to roles and organizational structures for each governance and management objective. A RACI chart consists of four components: enterprise roles and organizational structures, governance and management objectives, enterprise process practices and activities, and RACI assignments. The enterprise roles and organizational structures component should be updated to reflect the specific roles and structures that exist in the enterprise, as well as their names and descriptions.13 References: COBIT 2019 Framework: Introduction and Methodology, COBIT 2019 Framework: Roles, Responsibilities & RACI Charts