While planning an audit, an assessment of risk should be made to provide:
Correct Answer: A
Explanation/Reference: Explanation: The ISACA IS Auditing Guideline G15 on planning the IS audit states, 'An assessment of risk should be made to provide reasonable assurance that material items will be adequately covered during the audit work. This assessment should identify areas with a relatively high risk of the existence of material problems.' Definite assurance that material items will be covered during the audit work is an impractical proposition. Reasonable assurance that all items will be covered during the audit work is not the correct answer, as material items need to be covered, not all items.