At the completion of a system development project, a post project review should include which of the following?
Correct Answer: B
Explanation/Reference: Explanation: A project team has something to learn from each and every project. As risk assessment is a key issue for project management, it is important for the organization to accumulate lessons learned and integrate them into future projects. An assessment of potential downtime should be made with the operations group and other specialists before implementing a system. Verifying that controls are working should be covered during the acceptance test phase and possibly, again, in the post implementation review. Test data should be retained for future regression testing.