When reviewing an active project, an IS auditor observed that, because of a reduction in anticipated benefits and increased costs, the business case was no longer valid. The IS auditor should recommend that the:
Correct Answer: B
Explanation/Reference: Explanation: An IS auditor should not recommend discontinuing or completing the project before reviewing an updated business case. The IS auditor should recommend that the business case be kept current throughout the project since it is a key input to decisions made throughout the life of any project.