In addition to schedule, which other factor must be considered when evaluating changes to requirements?
Correct Answer: A
When evaluating changes to requirements, in addition to the schedule, it is crucial to consider the number of customers and end-users affected by the change. This factor is important because it directly impacts the value delivery and satisfaction of the stakeholders. The changes must align with the needs and expectations of the customers and end-users to ensure that the solution remains relevant and beneficial. Reference: This consideration is supported by the Business Analysis Body of Knowledge (BABOK) guide, which emphasizes the importance of stakeholder engagement and value delivery in the requirements management and communication knowledge area1.