Valid IIA-CIA-Part2 Dumps shared by ExamDiscuss.com for Helping Passing IIA-CIA-Part2 Exam! ExamDiscuss.com now offer the newest IIA-CIA-Part2 exam dumps, the ExamDiscuss.com IIA-CIA-Part2 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com IIA-CIA-Part2 dumps with Test Engine here:
Management has taken immediate action to address an observation received during an audit of the organization's manufacturing process Which of the following is true regarding the validity of the observation closure?
Correct Answer: A
Valid closure of an audit observation requires evidence that the corrected process will function as expected in the future. This involves not just addressing the immediate condition but also ensuring that the root cause has been addressed and that the implemented corrective actions are sustainable and effective in preventing recurrence. This ensures that the underlying issue has been resolved comprehensively. Reference: The IIA's International Standards for the Professional Practice of Internal Auditing (Standards), Standard 2500 - Monitoring Progress. The IIA's Practice Guide on Audit Follow-up.