<< Prev Question Next Question >>

Question 144/269

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.
This type of analysis is an example of which of the following?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (269q)
Question 1: After accepting and assigning a positive risk, risk owners h...
Question 2: A new stakeholder has been added to a project with a BAG of ...
Question 3: A PM has notified the project team of an immediate project r...
Question 4: A hurricane occurs in an area where several key project reso...
Question 5: A project sponsor approved an undocumented change without fo...
Question 6: A key team member found a new job and will be leaving in two...
Question 7: During the planning phase, the project manager meets with th...
Question 8: A project manager received a change request, immediately doc...
1 commentQuestion 9: A project manager needs a systems administrator as a resourc...
Question 10: A vendor who is scheduled to arrive in two days encounters a...
Question 11: Which of the following documents will MOST likely result in ...
Question 12: A project team member highlights to the project manager that...
Question 13: A milestone task on the critical path has been completed. Wh...
Question 14: A team member was replaced on a project by a new team member...
1 commentQuestion 15: A project manager is creating the monthly report for top man...
Question 16: A customer has requested a change in an active project. Whic...
Question 17: When a risk event occurs, which of the following documents i...
Question 18: Many Question: 01s have arisen regarding a newly identified ...
Question 19: A project manager is implementing a new edition of a magazin...
Question 20: Which of the following is a suitable situation in which to a...
Question 21: A project team is identifying, rating the probability of, an...
Question 22: The design team and development team disagree about what tec...
Question 23: A project in the execution phase is over budget, and tasks o...
Question 24: A sponsor requests that the project team shorten the complet...
Question 25: As part of the early stages of a potential corporate acquisi...
Question 26: Which of the following provides tools and standard documenta...
Question 27: A PM receives notification that an issue will impact a deliv...
Question 28: A project team learns that potential remodeling on the produ...
Question 29: A project manager has been experiencing resistance from a gr...
Question 30: The stakeholders who are available for the user acceptance t...
Question 31: Three IT companies have agreed to summarize their efforts as...
Question 32: A department manager asks a project manager about the status...
Question 33: Which of the following Agile ceremonies is used to determine...
Question 34: A critical issue has developed in an active project, and the...
Question 35: Which of the following describes how a project is related to...
Question 36: A project manager has identified a minor skills gap in the o...
Question 37: A software development project is struggling with a certain ...
Question 38: A project manager is scheduling activities and determines on...
1 commentQuestion 39: The project schedule performance index is 1.1, and the cost ...
Question 40: Which of the following are characteristics of qualitative ri...
Question 41: In a highway construction project, the project team has iden...
Question 42: A project team lacks the necessary team members to complete ...
Question 43: A program manager informs a project manager that a new, high...
Question 44: A sensitive project requires activities to occur with very s...
Question 45: There is a project in which the team can only meet once ever...
1 commentQuestion 46: A project team has just implemented an approved change to a ...
Question 47: A project manager has updated the risk register with the cur...
Question 48: During an active project, a meeting is set up to explain new...
Question 49: Which of the following events would MOST likely merit immedi...
Question 50: In the review of a project status report, the slack is negat...
Question 51: Which of the following events would MOST likely trigger comm...
Question 52: Joe, a stakeholder, threatens to withdraw from a project tha...
Question 53: A key stakeholder asked several members of the project team ...
Question 54: Which of the following methods should a project manager use ...
Question 55: A cost baseline is used to measure the:...
1 commentQuestion 56: Which of the following captures unforeseen activities throug...
Question 57: A project manager has established a series of virtual meetin...
Question 58: A fire occurred in the production facility over the weekend,...
Question 59: Despite receiving regular updates, a sponsor learns a projec...
Question 60: Which of the following is an example of a project?...
Question 61: When developing a project schedule, which of the following t...
Question 62: Midway through a project, the building the team works in is ...
Question 63: Which of the following describes a burn rate?...
Question 64: Which of the following is a key aspect of the Agile project ...
Question 65: Which of the following is a schedule that illustrates the du...
Question 66: Which of the following is the primary purpose of an MOA or a...
Question 67: A project manager is not going to finish a project on time b...
Question 68: The PMO has asked the PM to provide a status report indicati...
Question 69: Which of the following describes KPIs?...
Question 70: A project requires daily status updates. Which of the follow...
Question 71: Given the information in the table below, which of the follo...
Question 72: A software upgrade project has been postponed because it may...
Question 73: A project task has been completed ahead of schedule. Which o...
Question 74: A project manager notices a lack of meeting attendance from ...
Question 75: Which of the following organizational structures uses projec...
Question 76: An organization wants assurance that the specialty tools nec...
Question 77: An industry leader may be joining the project team and can p...
Question 78: A vendor is late with product deliverables. Which of the fol...
Question 79: A company engaged a third-party audit firm to provide regula...
Question 80: A project team received a memo stating no one can come into ...
1 commentQuestion 81: A major project task involves purchasing and implementing co...
Question 82: A project manager is managing a project with a hard deadline...
Question 83: Which of the following project phases occurs when requiremen...
Question 84: A project manager is developing a communication plan for an ...
Question 85: A project to implement Voice over Internet Protocol for a co...
Question 86: Gas prices were included in the cost baseline for a transpor...
Question 87: A project sponsor wants to know when the plan changed to shi...
Question 88: A project has been created, and the project team has been id...
Question 89: A project is coming to the end of a phase. The PMO required ...
Question 90: A project manager noted there were many possible features th...
Question 91: The project manager was asked to provide recommendations for...
Question 92: Which of the following project management roles is responsib...
Question 93: A project manager has requested the procurement department c...
Question 94: A project manager is working on the project charter. Which o...
Question 95: Which of the following should be updated FIRST, once the hur...
Question 96: A project manager provides status reports to a customer on a...
Question 97: Which of the following individuals is MOST likely to be a ke...
Question 98: In which of the following organizational structures would a ...
Question 99: A construction company has not been on the job for more than...
1 commentQuestion 100: A new project manager is working in an environment where res...
Question 101: Which of the following are characteristics of a project? (Ch...
Question 102: Risk ID 2 has occurred. (Exhibit) Which of the following way...
Question 103: Which of the following inherently affects quality standards?...
Question 104: Which of the following communication methods and target audi...
Question 105: A project sponsor promises the Chief Executive Officer (CEO)...
Question 106: A project manager must create documentation before the proje...
Question 107: A project manager has received documented approval from mana...
Question 108: Based on the table below: (Exhibit) Which of the following i...
Question 109: The anticipated funding level for an approved project was re...
Question 110: A project manager noticed the development team supporting a ...
Question 111: A new stakeholder has requested the status and progress repo...
Question 112: Which of the following is a risk strategy?...
Question 113: A new project manager would benefit from additional assistan...
Question 114: Which of the following includes setting governance gates as ...
Question 115: A project coordinator logs potential events that can affect ...
1 commentQuestion 116: Which of the following job roles is MOST responsible for pro...
Question 117: The project manager has had a large number of change request...
Question 118: Two team members are arguing over two different approaches t...
Question 119: In a projectized organization, a project manager has a need ...
Question 120: Which of the following is the BEST source for identifying th...
Question 121: When developing a project schedule, which of the following r...
Question 122: The project team is distributed throughout a single country....
Question 123: Tasks A, B, and C have a duration of two days. Task D has a ...
Question 124: A project manager is determining a project's critical path t...
Question 125: The project team is not comfortable moving an expensive mate...
Question 126: Company A recently partnered with Company B. Over the past f...
Question 127: A project team member states that the tasks identified in th...
Question 128: Which of the following documents ensures two parties do not ...
Question 129: A company recently went through a project requiring new equi...
Question 130: A senior manager asks a project manager for an estimated bud...
Question 131: Stakeholders often do not understand the hierarchy of roles ...
Question 132: Due to a new government regulation, a project change is requ...
Question 133: A project manager notices several of the action items discus...
Question 134: Two highly skilled resources, who are currently working on o...
Question 135: In which of the following circumstances would faxing be the ...
Question 136: Which of the following shows projected project expenditures?...
Question 137: Which of the following represents additional unauthorized re...
Question 138: The key stakeholders have reported the project pace as being...
Question 139: Which of the following would MOST likely be considered a pro...
Question 140: Expenditure tracking helps with cost:...
Question 141: During the planning phase of a construction project, the pro...
Question 142: A functional manager pulled a resource from a current projec...
Question 143: A company has hired a new project manager. The PMO has brief...
Question 144: The project manager is reviewing the earned value of work co...
Question 145: Which of the following measurements would give the project m...
Question 146: The project's network map has a loop with multiple project o...
Question 147: A critical stakeholder has requested additional status updat...
Question 148: A key stakeholder has communicated a significant project sco...
Question 149: A project manager decides to release a product one month lat...
Question 150: A project team is comprised of a mix of in-house and virtual...
Question 151: A company has completed its annual strategic planning sessio...
Question 152: During planning, a project coordinator publishes the project...
Question 153: In which of the following categories does a business process...
Question 154: A project manager recently joined a projectized organization...
Question 155: A project manager is informed that a team member would like ...
Question 156: A member of a CCB notices a change request was not approved ...
Question 157: A project manager is trying to ensure the quality of the des...
Question 158: A project team is in the process of risk planning. One of th...
Question 159: A minor change to the baseline schedule is required. This ch...
Question 160: Which of the following information does the project risk reg...
Question 161: Two team members approach a project manager with different i...
Question 162: Which of the following is a reason for assessing risk in a p...
Question 163: A project team member informs the project manager that a tas...
Question 164: As part of a project, employee production cannot proceed unl...
Question 165: A project has activities on the critical path that must be c...
Question 166: A company was originally organized using a functional struct...
Question 167: A key stakeholder cannot identify within the resource manage...
Question 168: Which of the following is the MOST likely target audience to...
Question 169: One of the tasks on a project's critical path is progressing...
Question 170: Which of the following is the BEST technique for comparing a...
Question 171: On larger projects, a vendor may occasionally proceed upon r...
Question 172: Based on the table below: (Exhibit) Which of the following i...
Question 173: A stakeholder wants to add four more data entry points on th...
Question 174: An agreement document that is intended to prevent two or mor...
Question 175: A project schedule lists a resource as 50% because it likely...
Question 176: Which of the following is the project phase when quality ass...
Question 177: A project sponsor wants to know which tasks are next in the ...
Question 178: A diagram or chart is required to illustrate data difference...
Question 179: A project manager is working on a project, which needs to be...
Question 180: A customer is in the early planning stages of a technology r...
Question 181: A project manager has taken over a project that is already i...
Question 182: Which of the following activities is MOST likely to be compl...
Question 183: A project sponsor informs the project manager that the proje...
Question 184: A senior developer abruptly resigned without notice. Because...
Question 185: A quality auditor finds suspicious code during a software te...
Question 186: Team members have reported poor sound quality during critica...
Question 187: A project manager wants to ensure that a detailed overview o...
Question 188: A project encountered a problem and reached a milestone. In ...
Question 189: Which of the following job roles is primarily tasked with co...
1 commentQuestion 190: Which of the following documents are considered mutually bin...
Question 191: A project manager has developed the initial schedule for an ...
Question 192: A project manager is meeting with top management executives ...
Question 193: A project manager has set aside a contingency reserve for un...
Question 194: Which of the following is a team-building stage that involve...
Question 195: Which of the following resources outlines consequences of no...
Question 196: Which of the following is MOST commonly associated with the ...
Question 197: The project team is creating a schedule for an upcoming proj...
Question 198: The project sponsor wishes to implement a 24/7 solution for ...
Question 199: A stakeholder is unaware of a project's status. Which of the...
Question 200: The Chief Executive Officer (CEO) informs the project manage...
Question 201: Team members in a projectized organization are released at t...
Question 202: Which of the following is a document that new employees at a...
Question 203: Which of the following are mutually binding project document...
Question 204: A project team is not delivering their tasks in a timely man...
Question 205: A project manager has noticed poor attendance as status meet...
Question 206: Which of the following is a characteristics of a matrix orga...
Question 207: An American publisher is participating in a workshop in Hong...
Question 208: The quarterly financial statement has been released, and por...
Question 209: During the risk assessment process, the qualitative analysis...
Question 210: A project manager, who previously worked at a construction f...
1 commentQuestion 211: An approved change was implemented. Which of the following s...
Question 212: A project has just begun, and people are not clear about the...
Question 213: A carpenter on a project team reports there is insufficient ...
1 commentQuestion 214: The PM is preparing for the planning phase kickoff meeting. ...
Question 215: Which of the following are major characteristics of sprint p...
Question 216: An audit, project change, task initiation/completion, gate r...
Question 217: Which of the following charts is a graphical representation ...
Question 218: A project has just finished performance testing and found th...
Question 219: Which of the following documents need to be updated as event...
Question 220: A team member has completed an assigned task. Which of the f...
Question 221: The project sponsor has cut the resources required for proje...
Question 222: The internal project sponsor is frustrated by a lack of conc...
Question 223: A project's stakeholders have not been informed of project u...
Question 224: A Chief Executive Officer (CEO) has approached a project tea...
Question 225: Based on the table below: (Exhibit) Which of the following i...
Question 226: A vendor is unable to deliver an order by the specified date...
Question 227: An organization has determined that all projects must use a ...
Question 228: A team member has reported Task 3 will be completed ahead of...
Question 229: Which of the following is the BEST indicator of project fail...
Question 230: A project facilitator is working within a large project team...
Question 231: Which of the following documents should be used FIRST when a...
Question 232: A project requires the distribution of training materials fo...
Question 233: A highly skilled project engineer will be on indefinite medi...
Question 234: An external customer has requested a modification of the pro...
Question 235: Which of the following represents the order of the team deve...
Question 236: Which of the following are the roles involved in a Scrum pro...
Question 237: A project team has completed a major deliverable earlier tha...
Question 238: In a Scrum retrospective, which of the following categories ...
Question 239: A project manager detects low performance from a team member...
Question 240: A project is due to deliver, configure, and install a collec...
Question 241: A project manager is overseeing an outsourced team of contra...
Question 242: A task on the critical path has just been completed. The pro...
Question 243: During an active project, the finished deliverables become s...
Question 244: Input into a project's requirements is needed for clarificat...
Question 245: A company purchased a parachute supplier and is now sending ...
Question 246: A change must be made to a project to comply with municipal ...
Question 247: A recently added stakeholder is unaware of critical changes ...
Question 248: A company decides to give a large section of its development...
Question 249: As a project processes, the team appears disjointed. Meeting...
Question 250: A project manager needs to determine resource availability t...
Question 251: A project sponsor would like the status of a key deliverable...
Question 252: The PMO is confused by an entry in the risk register and wou...
Question 253: A project team is preparing for a major system upgrade that ...
Question 254: Which of the following is the first document issued during t...
Question 255: Which of the following should a project manager consider as ...
Question 256: A project is nearing the expected completion date, but it is...
Question 257: In a weak matrix, a highly skilled project team member has b...
Question 258: A project manager is planning to hold a meeting to discuss w...
Question 259: While starting a new project, management is aligning the pro...
Question 260: Which of the following is the MOST appropriate communication...
Question 261: A company hires a number of interns and assigns them key rol...
Question 262: The PMO has removed a vendor from a project for inflating co...
1 commentQuestion 263: Given the following sprint: (Exhibit) Which of the following...
Question 264: Two parties are beginning conversations regarding the purcha...
Question 265: A small company has a successful proof of concept for an inn...
Question 266: A local company is part of a hostile takeover by a multinati...
Question 267: Which of the following is the MOST important component again...
1 commentQuestion 268: The Chief Executive Officer (CEO) has announced that the har...
Question 269: A project manager is analyzing the cost variances produced w...