Valid PK0-004 Dumps shared by ExamDiscuss.com for Helping Passing PK0-004 Exam! ExamDiscuss.com now offer the newest PK0-004 exam dumps, the ExamDiscuss.com PK0-004 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-004 dumps with Test Engine here:

Access PK0-004 Dumps Premium Version
(797 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 169/269

One of the tasks on a project's critical path is progressing too slowly. The team member who is responsible for completing the task is assigned to multiple projects with aggressive deadlines.
Which of the following roles has the responsibility of resolving the issue?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (269q)
Question 1: After accepting and assigning a positive risk, risk owners h...
Question 2: A new stakeholder has been added to a project with a BAG of ...
Question 3: A PM has notified the project team of an immediate project r...
Question 4: A hurricane occurs in an area where several key project reso...
Question 5: A project sponsor approved an undocumented change without fo...
Question 6: A key team member found a new job and will be leaving in two...
Question 7: During the planning phase, the project manager meets with th...
Question 8: A project manager received a change request, immediately doc...
1 commentQuestion 9: A project manager needs a systems administrator as a resourc...
Question 10: A vendor who is scheduled to arrive in two days encounters a...
Question 11: Which of the following documents will MOST likely result in ...
Question 12: A project team member highlights to the project manager that...
Question 13: A milestone task on the critical path has been completed. Wh...
Question 14: A team member was replaced on a project by a new team member...
1 commentQuestion 15: A project manager is creating the monthly report for top man...
Question 16: A customer has requested a change in an active project. Whic...
Question 17: When a risk event occurs, which of the following documents i...
Question 18: Many Question: 01s have arisen regarding a newly identified ...
Question 19: A project manager is implementing a new edition of a magazin...
Question 20: Which of the following is a suitable situation in which to a...
Question 21: A project team is identifying, rating the probability of, an...
Question 22: The design team and development team disagree about what tec...
Question 23: A project in the execution phase is over budget, and tasks o...
Question 24: A sponsor requests that the project team shorten the complet...
Question 25: As part of the early stages of a potential corporate acquisi...
Question 26: Which of the following provides tools and standard documenta...
Question 27: A PM receives notification that an issue will impact a deliv...
Question 28: A project team learns that potential remodeling on the produ...
Question 29: A project manager has been experiencing resistance from a gr...
Question 30: The stakeholders who are available for the user acceptance t...
Question 31: Three IT companies have agreed to summarize their efforts as...
Question 32: A department manager asks a project manager about the status...
Question 33: Which of the following Agile ceremonies is used to determine...
Question 34: A critical issue has developed in an active project, and the...
Question 35: Which of the following describes how a project is related to...
Question 36: A project manager has identified a minor skills gap in the o...
Question 37: A software development project is struggling with a certain ...
Question 38: A project manager is scheduling activities and determines on...
1 commentQuestion 39: The project schedule performance index is 1.1, and the cost ...
Question 40: Which of the following are characteristics of qualitative ri...
Question 41: In a highway construction project, the project team has iden...
Question 42: A project team lacks the necessary team members to complete ...
Question 43: A program manager informs a project manager that a new, high...
Question 44: A sensitive project requires activities to occur with very s...
Question 45: There is a project in which the team can only meet once ever...
1 commentQuestion 46: A project team has just implemented an approved change to a ...
Question 47: A project manager has updated the risk register with the cur...
Question 48: During an active project, a meeting is set up to explain new...
Question 49: Which of the following events would MOST likely merit immedi...
Question 50: In the review of a project status report, the slack is negat...
Question 51: Which of the following events would MOST likely trigger comm...
Question 52: Joe, a stakeholder, threatens to withdraw from a project tha...
Question 53: A key stakeholder asked several members of the project team ...
Question 54: Which of the following methods should a project manager use ...
Question 55: A cost baseline is used to measure the:...
1 commentQuestion 56: Which of the following captures unforeseen activities throug...
Question 57: A project manager has established a series of virtual meetin...
Question 58: A fire occurred in the production facility over the weekend,...
Question 59: Despite receiving regular updates, a sponsor learns a projec...
Question 60: Which of the following is an example of a project?...
Question 61: When developing a project schedule, which of the following t...
Question 62: Midway through a project, the building the team works in is ...
Question 63: Which of the following describes a burn rate?...
Question 64: Which of the following is a key aspect of the Agile project ...
Question 65: Which of the following is a schedule that illustrates the du...
Question 66: Which of the following is the primary purpose of an MOA or a...
Question 67: A project manager is not going to finish a project on time b...
Question 68: The PMO has asked the PM to provide a status report indicati...
Question 69: Which of the following describes KPIs?...
Question 70: A project requires daily status updates. Which of the follow...
Question 71: Given the information in the table below, which of the follo...
Question 72: A software upgrade project has been postponed because it may...
Question 73: A project task has been completed ahead of schedule. Which o...
Question 74: A project manager notices a lack of meeting attendance from ...
Question 75: Which of the following organizational structures uses projec...
Question 76: An organization wants assurance that the specialty tools nec...
Question 77: An industry leader may be joining the project team and can p...
Question 78: A vendor is late with product deliverables. Which of the fol...
Question 79: A company engaged a third-party audit firm to provide regula...
Question 80: A project team received a memo stating no one can come into ...
1 commentQuestion 81: A major project task involves purchasing and implementing co...
Question 82: A project manager is managing a project with a hard deadline...
Question 83: Which of the following project phases occurs when requiremen...
Question 84: A project manager is developing a communication plan for an ...
Question 85: A project to implement Voice over Internet Protocol for a co...
Question 86: Gas prices were included in the cost baseline for a transpor...
Question 87: A project sponsor wants to know when the plan changed to shi...
Question 88: A project has been created, and the project team has been id...
Question 89: A project is coming to the end of a phase. The PMO required ...
Question 90: A project manager noted there were many possible features th...
Question 91: The project manager was asked to provide recommendations for...
Question 92: Which of the following project management roles is responsib...
Question 93: A project manager has requested the procurement department c...
Question 94: A project manager is working on the project charter. Which o...
Question 95: Which of the following should be updated FIRST, once the hur...
Question 96: A project manager provides status reports to a customer on a...
Question 97: Which of the following individuals is MOST likely to be a ke...
Question 98: In which of the following organizational structures would a ...
Question 99: A construction company has not been on the job for more than...
1 commentQuestion 100: A new project manager is working in an environment where res...
Question 101: Which of the following are characteristics of a project? (Ch...
Question 102: Risk ID 2 has occurred. (Exhibit) Which of the following way...
Question 103: Which of the following inherently affects quality standards?...
Question 104: Which of the following communication methods and target audi...
Question 105: A project sponsor promises the Chief Executive Officer (CEO)...
Question 106: A project manager must create documentation before the proje...
Question 107: A project manager has received documented approval from mana...
Question 108: Based on the table below: (Exhibit) Which of the following i...
Question 109: The anticipated funding level for an approved project was re...
Question 110: A project manager noticed the development team supporting a ...
Question 111: A new stakeholder has requested the status and progress repo...
Question 112: Which of the following is a risk strategy?...
Question 113: A new project manager would benefit from additional assistan...
Question 114: Which of the following includes setting governance gates as ...
Question 115: A project coordinator logs potential events that can affect ...
1 commentQuestion 116: Which of the following job roles is MOST responsible for pro...
Question 117: The project manager has had a large number of change request...
Question 118: Two team members are arguing over two different approaches t...
Question 119: In a projectized organization, a project manager has a need ...
Question 120: Which of the following is the BEST source for identifying th...
Question 121: When developing a project schedule, which of the following r...
Question 122: The project team is distributed throughout a single country....
Question 123: Tasks A, B, and C have a duration of two days. Task D has a ...
Question 124: A project manager is determining a project's critical path t...
Question 125: The project team is not comfortable moving an expensive mate...
Question 126: Company A recently partnered with Company B. Over the past f...
Question 127: A project team member states that the tasks identified in th...
Question 128: Which of the following documents ensures two parties do not ...
Question 129: A company recently went through a project requiring new equi...
Question 130: A senior manager asks a project manager for an estimated bud...
Question 131: Stakeholders often do not understand the hierarchy of roles ...
Question 132: Due to a new government regulation, a project change is requ...
Question 133: A project manager notices several of the action items discus...
Question 134: Two highly skilled resources, who are currently working on o...
Question 135: In which of the following circumstances would faxing be the ...
Question 136: Which of the following shows projected project expenditures?...
Question 137: Which of the following represents additional unauthorized re...
Question 138: The key stakeholders have reported the project pace as being...
Question 139: Which of the following would MOST likely be considered a pro...
Question 140: Expenditure tracking helps with cost:...
Question 141: During the planning phase of a construction project, the pro...
Question 142: A functional manager pulled a resource from a current projec...
Question 143: A company has hired a new project manager. The PMO has brief...
Question 144: The project manager is reviewing the earned value of work co...
Question 145: Which of the following measurements would give the project m...
Question 146: The project's network map has a loop with multiple project o...
Question 147: A critical stakeholder has requested additional status updat...
Question 148: A key stakeholder has communicated a significant project sco...
Question 149: A project manager decides to release a product one month lat...
Question 150: A project team is comprised of a mix of in-house and virtual...
Question 151: A company has completed its annual strategic planning sessio...
Question 152: During planning, a project coordinator publishes the project...
Question 153: In which of the following categories does a business process...
Question 154: A project manager recently joined a projectized organization...
Question 155: A project manager is informed that a team member would like ...
Question 156: A member of a CCB notices a change request was not approved ...
Question 157: A project manager is trying to ensure the quality of the des...
Question 158: A project team is in the process of risk planning. One of th...
Question 159: A minor change to the baseline schedule is required. This ch...
Question 160: Which of the following information does the project risk reg...
Question 161: Two team members approach a project manager with different i...
Question 162: Which of the following is a reason for assessing risk in a p...
Question 163: A project team member informs the project manager that a tas...
Question 164: As part of a project, employee production cannot proceed unl...
Question 165: A project has activities on the critical path that must be c...
Question 166: A company was originally organized using a functional struct...
Question 167: A key stakeholder cannot identify within the resource manage...
Question 168: Which of the following is the MOST likely target audience to...
Question 169: One of the tasks on a project's critical path is progressing...
Question 170: Which of the following is the BEST technique for comparing a...
Question 171: On larger projects, a vendor may occasionally proceed upon r...
Question 172: Based on the table below: (Exhibit) Which of the following i...
Question 173: A stakeholder wants to add four more data entry points on th...
Question 174: An agreement document that is intended to prevent two or mor...
Question 175: A project schedule lists a resource as 50% because it likely...
Question 176: Which of the following is the project phase when quality ass...
Question 177: A project sponsor wants to know which tasks are next in the ...
Question 178: A diagram or chart is required to illustrate data difference...
Question 179: A project manager is working on a project, which needs to be...
Question 180: A customer is in the early planning stages of a technology r...
Question 181: A project manager has taken over a project that is already i...
Question 182: Which of the following activities is MOST likely to be compl...
Question 183: A project sponsor informs the project manager that the proje...
Question 184: A senior developer abruptly resigned without notice. Because...
Question 185: A quality auditor finds suspicious code during a software te...
Question 186: Team members have reported poor sound quality during critica...
Question 187: A project manager wants to ensure that a detailed overview o...
Question 188: A project encountered a problem and reached a milestone. In ...
Question 189: Which of the following job roles is primarily tasked with co...
1 commentQuestion 190: Which of the following documents are considered mutually bin...
Question 191: A project manager has developed the initial schedule for an ...
Question 192: A project manager is meeting with top management executives ...
Question 193: A project manager has set aside a contingency reserve for un...
Question 194: Which of the following is a team-building stage that involve...
Question 195: Which of the following resources outlines consequences of no...
Question 196: Which of the following is MOST commonly associated with the ...
Question 197: The project team is creating a schedule for an upcoming proj...
Question 198: The project sponsor wishes to implement a 24/7 solution for ...
Question 199: A stakeholder is unaware of a project's status. Which of the...
Question 200: The Chief Executive Officer (CEO) informs the project manage...
Question 201: Team members in a projectized organization are released at t...
Question 202: Which of the following is a document that new employees at a...
Question 203: Which of the following are mutually binding project document...
Question 204: A project team is not delivering their tasks in a timely man...
Question 205: A project manager has noticed poor attendance as status meet...
Question 206: Which of the following is a characteristics of a matrix orga...
Question 207: An American publisher is participating in a workshop in Hong...
Question 208: The quarterly financial statement has been released, and por...
Question 209: During the risk assessment process, the qualitative analysis...
Question 210: A project manager, who previously worked at a construction f...
1 commentQuestion 211: An approved change was implemented. Which of the following s...
Question 212: A project has just begun, and people are not clear about the...
Question 213: A carpenter on a project team reports there is insufficient ...
1 commentQuestion 214: The PM is preparing for the planning phase kickoff meeting. ...
Question 215: Which of the following are major characteristics of sprint p...
Question 216: An audit, project change, task initiation/completion, gate r...
Question 217: Which of the following charts is a graphical representation ...
Question 218: A project has just finished performance testing and found th...
Question 219: Which of the following documents need to be updated as event...
Question 220: A team member has completed an assigned task. Which of the f...
Question 221: The project sponsor has cut the resources required for proje...
Question 222: The internal project sponsor is frustrated by a lack of conc...
Question 223: A project's stakeholders have not been informed of project u...
Question 224: A Chief Executive Officer (CEO) has approached a project tea...
Question 225: Based on the table below: (Exhibit) Which of the following i...
Question 226: A vendor is unable to deliver an order by the specified date...
Question 227: An organization has determined that all projects must use a ...
Question 228: A team member has reported Task 3 will be completed ahead of...
Question 229: Which of the following is the BEST indicator of project fail...
Question 230: A project facilitator is working within a large project team...
Question 231: Which of the following documents should be used FIRST when a...
Question 232: A project requires the distribution of training materials fo...
Question 233: A highly skilled project engineer will be on indefinite medi...
Question 234: An external customer has requested a modification of the pro...
Question 235: Which of the following represents the order of the team deve...
Question 236: Which of the following are the roles involved in a Scrum pro...
Question 237: A project team has completed a major deliverable earlier tha...
Question 238: In a Scrum retrospective, which of the following categories ...
Question 239: A project manager detects low performance from a team member...
Question 240: A project is due to deliver, configure, and install a collec...
Question 241: A project manager is overseeing an outsourced team of contra...
Question 242: A task on the critical path has just been completed. The pro...
Question 243: During an active project, the finished deliverables become s...
Question 244: Input into a project's requirements is needed for clarificat...
Question 245: A company purchased a parachute supplier and is now sending ...
Question 246: A change must be made to a project to comply with municipal ...
Question 247: A recently added stakeholder is unaware of critical changes ...
Question 248: A company decides to give a large section of its development...
Question 249: As a project processes, the team appears disjointed. Meeting...
Question 250: A project manager needs to determine resource availability t...
Question 251: A project sponsor would like the status of a key deliverable...
Question 252: The PMO is confused by an entry in the risk register and wou...
Question 253: A project team is preparing for a major system upgrade that ...
Question 254: Which of the following is the first document issued during t...
Question 255: Which of the following should a project manager consider as ...
Question 256: A project is nearing the expected completion date, but it is...
Question 257: In a weak matrix, a highly skilled project team member has b...
Question 258: A project manager is planning to hold a meeting to discuss w...
Question 259: While starting a new project, management is aligning the pro...
Question 260: Which of the following is the MOST appropriate communication...
Question 261: A company hires a number of interns and assigns them key rol...
Question 262: The PMO has removed a vendor from a project for inflating co...
1 commentQuestion 263: Given the following sprint: (Exhibit) Which of the following...
Question 264: Two parties are beginning conversations regarding the purcha...
Question 265: A small company has a successful proof of concept for an inn...
Question 266: A local company is part of a hostile takeover by a multinati...
Question 267: Which of the following is the MOST important component again...
1 commentQuestion 268: The Chief Executive Officer (CEO) has announced that the har...
Question 269: A project manager is analyzing the cost variances produced w...