Which of the following is primarily responsible for developing the timeline?
Correct Answer: D
The project scheduler is responsible for developing and maintaining the project schedule, communicating the timelines and due dates, reporting schedule performance, and communicating any schedule changes to the stakeholders and project team members." - Kim Heldman CompTIA Project+ Study Guide; 2nd Edition; Sybex; Indianapolis.