Valid PK0-004 Dumps shared by ExamDiscuss.com for Helping Passing PK0-004 Exam! ExamDiscuss.com now offer the newest PK0-004 exam dumps, the ExamDiscuss.com PK0-004 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-004 dumps with Test Engine here:

Access PK0-004 Dumps Premium Version
(797 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 172/247

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:
Coordinate project schedule
Manage to the triple constraint
Provide performance feedback to team members' managers
Which of the following types of organizational structures did the new project manager MOST likely join?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (247q)
Question 1: On an OBS chart, there is a dashed line between some team me...
Question 2: A Chief Executive Officer (CEO) has approached a project tea...
Question 3: A construction company has not been on the job for more than...
Question 4: Which of the following risk strategies prevents a risk from ...
Question 5: A project manager is informed that the project sponsor was t...
Question 6: Due to a new government regulation, a project change is requ...
Question 7: A software development project is struggling with a certain ...
Question 8: A project team is showing off a new product prototype at a t...
Question 9: A project has a BAC of $850,000. The project manager has ide...
Question 10: A project has fallen behind schedule for no obvious reason, ...
Question 11: When a project team member completes a task in the WBS, whic...
Question 12: A project manager wants to ensure that a detailed overview o...
Question 13: A new stakeholder has been added to a project with a BAG of ...
Question 14: Ann, a project manager, is working for a new company. On her...
Question 15: A new corporate policy was approved that will positively aff...
Question 16: A project needs two more months of work to be completed, but...
Question 17: Task ID 3 did not start on time, and no work has been accomp...
Question 18: A key stakeholder cannot identify within the resource manage...
Question 19: Using Scrum, which of the following are discussed in a daily...
Question 20: At each project team meeting, the project team raises the sa...
Question 21: A new project manager is assigned in the middle of a seven-m...
Question 22: A project sponsor is not being updated on the project as exp...
Question 23: Which of the following is a definition of an RFP?...
Question 24: Ann, a customer, approaches the project manager of a portabl...
Question 25: Three IT companies have agreed to summarize their efforts as...
Question 26: Which of the following is a schedule that illustrates the du...
Question 27: Rather than sending emails to communicate all project inform...
Question 28: Near the end of a sprint, the IT systems were taken down for...
Question 29: A stakeholder is unaware of a project's status. Which of the...
Question 30: A project manager recently joined a projectized organization...
Question 31: A company hires an outside vendor to provide 24/7 support. W...
Question 32: While working on a project, a self-organized team determines...
Question 33: A project team is brainstorming and documenting what might g...
Question 34: A project team added a new member who has proprietary inform...
Question 35: A sponsor requests that the project team shorten the complet...
Question 36: The project sponsor wishes to implement a 24/7 solution for ...
Question 37: A project sponsor approved an undocumented change without fo...
Question 38: A senior developer abruptly resigned without notice. Because...
Question 39: Which of the following is primarily responsible for developi...
Question 40: The PMO has removed a vendor from a project for inflating co...
Question 41: A vendor developed a new payroll system for a local transit ...
Question 42: An approved change was implemented. Which of the following s...
Question 43: The responsibility of estimating how long a task will take b...
Question 44: A stakeholder informs a project manager that a weekly status...
Question 45: While developing a project schedule, the project manager is ...
Question 46: A project manager is implementing a new edition of a magazin...
Question 47: A project sponsor decides to cut the project budget and redu...
Question 48: The project team is distributed throughout a single country....
Question 49: A company's management team is in a meeting to review all th...
Question 50: After accepting and assigning a positive risk, risk owners h...
Question 51: A stakeholder with whom the project manager has worked on nu...
Question 52: A highly skilled, key project team member lacks technical wr...
Question 53: Which of the following describes risk mitigation?...
Question 54: A recently added stakeholder is unaware of critical changes ...
Question 55: A project manager is successfully adhering to an eight-week ...
Question 56: A part that is needed to complete Task 3 has been backordere...
Question 57: Which of the following communication methods and target audi...
Question 58: Task B is not planned to start until Task A is completed. Ta...
Question 59: A project needs to know if a project is progressing as plann...
Question 60: A new project charter is being drafted. Which of the followi...
Question 61: A project manager received a change request, immediately doc...
Question 62: A key stakeholder claims to have not received status updates...
Question 63: A project manager receives an initial project assignment. Wh...
Question 64: Two critical members have approached the project manager sep...
Question 65: A project manager needs to determine resource availability t...
Question 66: A project manager is assigned a global team. The project man...
Question 67: The supervisor asks an engineer to be a project manager with...
Question 68: A project manager is attempting to establish the proper sequ...
Question 69: A new stakeholder has joined the project team and requested ...
Question 70: The project manager is reviewing the earned value of work co...
Question 71: A project manager has laid out a network diagram and is begi...
Question 72: An organization wants assurance that the specialty tools nec...
Question 73: The project manager needs to motivate the team; however, is ...
Question 74: One deliverable failed during testing, and this has already ...
Question 75: When developing a project schedule, which of the following r...
Question 76: A project manager, who previously worked at a construction f...
Question 77: An influential stakeholder has left the organization. Which ...
Question 78: The vendor management team has requested all project manager...
Question 79: A key stakeholder asked several members of the project team ...
Question 80: A project manager is planning to hold a meeting to discuss w...
Question 81: A project manager creates a Pareto chart based on the table ...
Question 82: A project has fallen behind schedule. Upon investigation, th...
Question 83: Which of the following is the BEST method to provide quick s...
Question 84: A project manager identified a risk in a geographically unst...
Question 85: An industry leader may be joining the project team and can p...
Question 86: A project manager decides to release a product one month lat...
Question 87: While working with a project team to create the project sche...
Question 88: Which of the following can a project manager use to keep tra...
Question 89: Which of the following are mutually binding project document...
Question 90: A number of requirements, conflicts, and reworks during a pr...
Question 91: A project task has been completed ahead of schedule. Which o...
Question 92: A team member has been consistently underperforming, and men...
Question 93: The chairperson of the board is visiting from another countr...
Question 94: Tasks A and B have a duration of two days. Task A starts on ...
Question 95: A PM has notified the project team of an immediate project r...
Question 96: A WBS is being developed for a project. Which of the followi...
Question 97: A project sponsor would like the status of a key deliverable...
Question 98: Which of the following roles is MOST involved in checking th...
Question 99: Two team members have concluded that documentation is not re...
Question 100: A project manager is working on the project charter. Which o...
Question 101: A project to implement Voice over Internet Protocol for a co...
Question 102: Which of the following are MOST essential to developing an e...
Question 103: A software upgrade project has been postponed because it may...
Question 104: An active construction project must make immediate changes w...
Question 105: Which of the following organization types requires the proje...
Question 106: An external customer has requested a modification of the pro...
Question 107: A company just announced all third-party vendors must provid...
Question 108: A project manager has just received an extra resource from a...
Question 109: A project manager is reviewing documents to develop the proj...
Question 110: Which of the following normally would be completed prior to ...
Question 111: A highly skilled project engineer will be on indefinite medi...
Question 112: A contract review meeting has been scheduled with a non-perf...
Question 113: An authorized change to a construction project was implement...
Question 114: A new project sponsor has joined the project team, and the c...
Question 115: A manager is reviewing some projects with two project manage...
Question 116: A company accepts a proposal from a third-party vendor to pr...
Question 117: Which of the following project phases occurs when requiremen...
Question 118: After identifying all known tasks, the project manager has s...
Question 119: A fire alarm goes off in the building where the project team...
Question 120: Which of the following documents will MOST likely result in ...
Question 121: A project team is overseeing the installation of a new repti...
Question 122: A vendor notifies the project manager that the scheduled dat...
Question 123: A stakeholders asked for a change to the project. The projec...
Question 124: A project manager is creating the WBS. In which of the follo...
Question 125: A project manager is justifying a required change with the a...
Question 126: Which of the following are characteristics of a project? (Ch...
Question 127: Which of the following is used to perform a root cause analy...
Question 128: Management announces the PMO will assume all research and de...
Question 129: Which of the following organizational changes is MOST likely...
Question 130: Given the table below for a house construction project: (Exh...
Question 131: Which of the following would indicate a project manager is w...
Question 132: A customer has requested additional features for an active p...
Question 133: Which of the following are major characteristics of sprint p...
Question 134: A project manager is assigned to a project that was previous...
Question 135: A project manager notices a lack of meeting attendance from ...
Question 136: Which of the following methods should a project manager use ...
Question 137: A project manager has gathered time estimates for a new proj...
Question 138: In the review of a project status report, the slack is negat...
Question 139: Which of the following describes KPIs?...
Question 140: Given the following sprint: (Exhibit) Which of the following...
Question 141: A customer asks a project manager if a small change can be m...
Question 142: A hurricane occurs in an area where several key project reso...
Question 143: The executive sponsor asks a project manager to summarize th...
Question 144: A project sponsor has requested documentation to determine t...
Question 145: Which of the following documents would MOST likely provide a...
Question 146: An external consultant reviews benchmark staffing for an org...
Question 147: During a meeting, a new member of the PMO says, "If this pro...
Question 148: In a project with a BCA of $235,000, the CPI is 0.80, and th...
Question 149: A project team has determined it will need to source data fr...
Question 150: A vendor is unable to deliver an order by the specified date...
Question 151: Which of the following events would MOST likely trigger comm...
Question 152: Which of the following represents additional unauthorized re...
Question 153: A project manager is assigned to an ongoing project. Which o...
Question 154: Given the status report excerpt below: (Exhibit) Overall sta...
Question 155: A company recently discovered that it could save money by mo...
Question 156: A project in the execution phase is over budget, and tasks o...
Question 157: A company is about to initiate a cybersecurity project. Howe...
Question 158: When developing a project schedule, which of the following t...
Question 159: Team members have reported that meetings are poorly attended...
Question 160: Which of the following is the first document issued during t...
Question 161: A project coordinator logs potential events that can affect ...
Question 162: Which of the following elements should be included on a resp...
Question 163: A company has determined it does not have the in-house capab...
Question 164: A project manager needs a systems administrator as a resourc...
Question 165: Which of the following techniques modifies the schedule base...
Question 166: A project manager is reviewing project performance. Which of...
Question 167: The managing director of a law firm has asked the project ma...
Question 168: The project sponsor has cut the resources required for proje...
Question 169: Ann, one of the affected stakeholders, feels that the projec...
Question 170: Which of the following analyses should a project manager use...
Question 171: A developer is experiencing constant project scope changes a...
Question 172: A company has hired a new project manager. The PMO has brief...
Question 173: Which of the following is performed during the monitoring an...
Question 174: A senior developer abruptly resigned without notice. Because...
Question 175: A risk with minor impact has been realized. There is no chan...
Question 176: The project team has identified all the tasks needed to crea...
Question 177: A company has been trying to implement a product with multip...
Question 178: A project is in the initiation phase. Which of the following...
Question 179: Which of the following documents focus primarily on support ...
Question 180: The PMO is responsible for: (Choose two.)...
Question 181: Which of the following are characteristics of a matrix organ...
Question 182: A project is about to begin the execution phase. The SOW and...
Question 183: A vendor has accepted a proposed project from a customer. Wh...
Question 184: For most organizations, which of the following is the MOST e...
Question 185: Which of the following characteristics would stakeholders MO...
Question 186: Which of the following events would MOST likely merit immedi...
Question 187: The PMO has asked the PM to provide a status report indicati...
Question 188: A change must be made to a project to comply with municipal ...
Question 189: In a projectized organization, a project manager has a need ...
Question 190: When forming a project team, there are a number of phases. W...
Question 191: Which of the following should a project manager consider as ...
Question 192: The government wants to start a project that will launch a s...
Question 193: A project manager is overseeing the construction of a new bu...
Question 194: The Chief Executive Officer (CEO) of a company announced tha...
Question 195: Which of the following includes setting governance gates as ...
Question 196: A project manager at a projectized organization is resource ...
Question 197: Which of the following indicators would help the project man...
Question 198: Which of the following are the roles involved in a Scrum pro...
Question 199: A project scheduler has calculated the project's critical pa...
Question 200: Which of the following defines the minimum level of engageme...
Question 201: Which of the following is a characteristics of a matrix orga...
Question 202: A new project manager is working in an environment where res...
Question 203: A project manager has received a change order that will redu...
Question 204: In a weak matrix, a highly skilled project team member has b...
Question 205: Which of the following shows projected project expenditures?...
Question 206: A project team is creating a new product, and stakeholders a...
Question 207: A program manager informs a project manager that a new, high...
Question 208: An organization has multiple projects that are taking place ...
Question 209: Upper management asks a project sponsor to provide several a...
Question 210: Which of the following documents is typically signed by the ...
Question 211: A project manager is analyzing the cost variances produced w...
Question 212: A project manager detects low performance from a team member...
Question 213: A project manager is starting a project on an unfamiliar tec...
Question 214: A company's Chief Executive Officer (CEO) has asked the proj...
Question 215: Which of the following is the MOST appropriate communication...
Question 216: A project manager is meeting with top management executives ...
Question 217: An audit, project change, task initiation/completion, gate r...
Question 218: Top-level managers are considering joining certain projects,...
Question 219: A project manager is managing a project with a hard deadline...
Question 220: Which of the following inherently affects quality standards?...
Question 221: A project manager wants to introduce the practice of a WBS t...
Question 222: A project manager is managing an eight-month effort and has ...
Question 223: A functional manager pulled a resource from a current projec...
Question 224: The project's network map has a loop with multiple project o...
Question 225: A project requires daily status updates. Which of the follow...
Question 226: Joe, a project team member, was hired after a project was al...
Question 227: A project sponsor no longer wants to receive email communica...
Question 228: In which of the following situations is a project manager MO...
Question 229: A company is hired to perform some of another organization's...
Question 230: There is a project in which the team can only meet once ever...
Question 231: A first-time project manager is developing a project charter...
Question 232: Despite receiving regular updates, a sponsor learns a projec...
Question 233: A project is running behind schedule. To meet the delivery t...
Question 234: A customer will have ongoing changes to project requirements...
Question 235: Which of the following will identify the MOST potential proj...
Question 236: As a project processes, the team appears disjointed. Meeting...
Question 237: A project manager is reviewing a project's status and finds ...
Question 238: Which of the following is the BEST technique for comparing a...
Question 239: During a CCB, a SME evaluated the impact and provided new in...
Question 240: A project manager has contracted a third-party vendor to ach...
Question 241: A sports event is coming to a local city, and the project ma...
Question 242: An active project is focused on quality assurance of the del...
Question 243: Based on the table below: (Exhibit) Which of the following i...
Question 244: Which of the following job roles is MOST responsible for pro...
Question 245: A project team learns that potential remodeling on the produ...
Question 246: A project manager wishes to track a project's performance ag...
Question 247: Project B cannot start before Project A is complete, but Pro...