<< Prev Question Next Question >>

Question 90/247

A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts.
Which of the following is MOST likely the cause?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (247q)
Question 1: On an OBS chart, there is a dashed line between some team me...
Question 2: A Chief Executive Officer (CEO) has approached a project tea...
Question 3: A construction company has not been on the job for more than...
Question 4: Which of the following risk strategies prevents a risk from ...
Question 5: A project manager is informed that the project sponsor was t...
Question 6: Due to a new government regulation, a project change is requ...
Question 7: A software development project is struggling with a certain ...
Question 8: A project team is showing off a new product prototype at a t...
Question 9: A project has a BAC of $850,000. The project manager has ide...
Question 10: A project has fallen behind schedule for no obvious reason, ...
Question 11: When a project team member completes a task in the WBS, whic...
Question 12: A project manager wants to ensure that a detailed overview o...
Question 13: A new stakeholder has been added to a project with a BAG of ...
Question 14: Ann, a project manager, is working for a new company. On her...
Question 15: A new corporate policy was approved that will positively aff...
Question 16: A project needs two more months of work to be completed, but...
Question 17: Task ID 3 did not start on time, and no work has been accomp...
Question 18: A key stakeholder cannot identify within the resource manage...
Question 19: Using Scrum, which of the following are discussed in a daily...
Question 20: At each project team meeting, the project team raises the sa...
Question 21: A new project manager is assigned in the middle of a seven-m...
Question 22: A project sponsor is not being updated on the project as exp...
Question 23: Which of the following is a definition of an RFP?...
Question 24: Ann, a customer, approaches the project manager of a portabl...
Question 25: Three IT companies have agreed to summarize their efforts as...
Question 26: Which of the following is a schedule that illustrates the du...
Question 27: Rather than sending emails to communicate all project inform...
Question 28: Near the end of a sprint, the IT systems were taken down for...
Question 29: A stakeholder is unaware of a project's status. Which of the...
Question 30: A project manager recently joined a projectized organization...
Question 31: A company hires an outside vendor to provide 24/7 support. W...
Question 32: While working on a project, a self-organized team determines...
Question 33: A project team is brainstorming and documenting what might g...
Question 34: A project team added a new member who has proprietary inform...
Question 35: A sponsor requests that the project team shorten the complet...
Question 36: The project sponsor wishes to implement a 24/7 solution for ...
Question 37: A project sponsor approved an undocumented change without fo...
Question 38: A senior developer abruptly resigned without notice. Because...
Question 39: Which of the following is primarily responsible for developi...
Question 40: The PMO has removed a vendor from a project for inflating co...
Question 41: A vendor developed a new payroll system for a local transit ...
Question 42: An approved change was implemented. Which of the following s...
Question 43: The responsibility of estimating how long a task will take b...
Question 44: A stakeholder informs a project manager that a weekly status...
Question 45: While developing a project schedule, the project manager is ...
Question 46: A project manager is implementing a new edition of a magazin...
Question 47: A project sponsor decides to cut the project budget and redu...
Question 48: The project team is distributed throughout a single country....
Question 49: A company's management team is in a meeting to review all th...
Question 50: After accepting and assigning a positive risk, risk owners h...
Question 51: A stakeholder with whom the project manager has worked on nu...
Question 52: A highly skilled, key project team member lacks technical wr...
Question 53: Which of the following describes risk mitigation?...
Question 54: A recently added stakeholder is unaware of critical changes ...
Question 55: A project manager is successfully adhering to an eight-week ...
Question 56: A part that is needed to complete Task 3 has been backordere...
Question 57: Which of the following communication methods and target audi...
Question 58: Task B is not planned to start until Task A is completed. Ta...
Question 59: A project needs to know if a project is progressing as plann...
Question 60: A new project charter is being drafted. Which of the followi...
Question 61: A project manager received a change request, immediately doc...
Question 62: A key stakeholder claims to have not received status updates...
Question 63: A project manager receives an initial project assignment. Wh...
Question 64: Two critical members have approached the project manager sep...
Question 65: A project manager needs to determine resource availability t...
Question 66: A project manager is assigned a global team. The project man...
Question 67: The supervisor asks an engineer to be a project manager with...
Question 68: A project manager is attempting to establish the proper sequ...
Question 69: A new stakeholder has joined the project team and requested ...
Question 70: The project manager is reviewing the earned value of work co...
Question 71: A project manager has laid out a network diagram and is begi...
Question 72: An organization wants assurance that the specialty tools nec...
Question 73: The project manager needs to motivate the team; however, is ...
Question 74: One deliverable failed during testing, and this has already ...
Question 75: When developing a project schedule, which of the following r...
Question 76: A project manager, who previously worked at a construction f...
Question 77: An influential stakeholder has left the organization. Which ...
Question 78: The vendor management team has requested all project manager...
Question 79: A key stakeholder asked several members of the project team ...
Question 80: A project manager is planning to hold a meeting to discuss w...
Question 81: A project manager creates a Pareto chart based on the table ...
Question 82: A project has fallen behind schedule. Upon investigation, th...
Question 83: Which of the following is the BEST method to provide quick s...
Question 84: A project manager identified a risk in a geographically unst...
Question 85: An industry leader may be joining the project team and can p...
Question 86: A project manager decides to release a product one month lat...
Question 87: While working with a project team to create the project sche...
Question 88: Which of the following can a project manager use to keep tra...
Question 89: Which of the following are mutually binding project document...
Question 90: A number of requirements, conflicts, and reworks during a pr...
Question 91: A project task has been completed ahead of schedule. Which o...
Question 92: A team member has been consistently underperforming, and men...
Question 93: The chairperson of the board is visiting from another countr...
Question 94: Tasks A and B have a duration of two days. Task A starts on ...
Question 95: A PM has notified the project team of an immediate project r...
Question 96: A WBS is being developed for a project. Which of the followi...
Question 97: A project sponsor would like the status of a key deliverable...
Question 98: Which of the following roles is MOST involved in checking th...
Question 99: Two team members have concluded that documentation is not re...
Question 100: A project manager is working on the project charter. Which o...
Question 101: A project to implement Voice over Internet Protocol for a co...
Question 102: Which of the following are MOST essential to developing an e...
Question 103: A software upgrade project has been postponed because it may...
Question 104: An active construction project must make immediate changes w...
Question 105: Which of the following organization types requires the proje...
Question 106: An external customer has requested a modification of the pro...
Question 107: A company just announced all third-party vendors must provid...
Question 108: A project manager has just received an extra resource from a...
Question 109: A project manager is reviewing documents to develop the proj...
Question 110: Which of the following normally would be completed prior to ...
Question 111: A highly skilled project engineer will be on indefinite medi...
Question 112: A contract review meeting has been scheduled with a non-perf...
Question 113: An authorized change to a construction project was implement...
Question 114: A new project sponsor has joined the project team, and the c...
Question 115: A manager is reviewing some projects with two project manage...
Question 116: A company accepts a proposal from a third-party vendor to pr...
Question 117: Which of the following project phases occurs when requiremen...
Question 118: After identifying all known tasks, the project manager has s...
Question 119: A fire alarm goes off in the building where the project team...
Question 120: Which of the following documents will MOST likely result in ...
Question 121: A project team is overseeing the installation of a new repti...
Question 122: A vendor notifies the project manager that the scheduled dat...
Question 123: A stakeholders asked for a change to the project. The projec...
Question 124: A project manager is creating the WBS. In which of the follo...
Question 125: A project manager is justifying a required change with the a...
Question 126: Which of the following are characteristics of a project? (Ch...
Question 127: Which of the following is used to perform a root cause analy...
Question 128: Management announces the PMO will assume all research and de...
Question 129: Which of the following organizational changes is MOST likely...
Question 130: Given the table below for a house construction project: (Exh...
Question 131: Which of the following would indicate a project manager is w...
Question 132: A customer has requested additional features for an active p...
Question 133: Which of the following are major characteristics of sprint p...
Question 134: A project manager is assigned to a project that was previous...
Question 135: A project manager notices a lack of meeting attendance from ...
Question 136: Which of the following methods should a project manager use ...
Question 137: A project manager has gathered time estimates for a new proj...
Question 138: In the review of a project status report, the slack is negat...
Question 139: Which of the following describes KPIs?...
Question 140: Given the following sprint: (Exhibit) Which of the following...
Question 141: A customer asks a project manager if a small change can be m...
Question 142: A hurricane occurs in an area where several key project reso...
Question 143: The executive sponsor asks a project manager to summarize th...
Question 144: A project sponsor has requested documentation to determine t...
Question 145: Which of the following documents would MOST likely provide a...
Question 146: An external consultant reviews benchmark staffing for an org...
Question 147: During a meeting, a new member of the PMO says, "If this pro...
Question 148: In a project with a BCA of $235,000, the CPI is 0.80, and th...
Question 149: A project team has determined it will need to source data fr...
Question 150: A vendor is unable to deliver an order by the specified date...
Question 151: Which of the following events would MOST likely trigger comm...
Question 152: Which of the following represents additional unauthorized re...
Question 153: A project manager is assigned to an ongoing project. Which o...
Question 154: Given the status report excerpt below: (Exhibit) Overall sta...
Question 155: A company recently discovered that it could save money by mo...
Question 156: A project in the execution phase is over budget, and tasks o...
Question 157: A company is about to initiate a cybersecurity project. Howe...
Question 158: When developing a project schedule, which of the following t...
Question 159: Team members have reported that meetings are poorly attended...
Question 160: Which of the following is the first document issued during t...
Question 161: A project coordinator logs potential events that can affect ...
Question 162: Which of the following elements should be included on a resp...
Question 163: A company has determined it does not have the in-house capab...
Question 164: A project manager needs a systems administrator as a resourc...
Question 165: Which of the following techniques modifies the schedule base...
Question 166: A project manager is reviewing project performance. Which of...
Question 167: The managing director of a law firm has asked the project ma...
Question 168: The project sponsor has cut the resources required for proje...
Question 169: Ann, one of the affected stakeholders, feels that the projec...
Question 170: Which of the following analyses should a project manager use...
Question 171: A developer is experiencing constant project scope changes a...
Question 172: A company has hired a new project manager. The PMO has brief...
Question 173: Which of the following is performed during the monitoring an...
Question 174: A senior developer abruptly resigned without notice. Because...
Question 175: A risk with minor impact has been realized. There is no chan...
Question 176: The project team has identified all the tasks needed to crea...
Question 177: A company has been trying to implement a product with multip...
Question 178: A project is in the initiation phase. Which of the following...
Question 179: Which of the following documents focus primarily on support ...
Question 180: The PMO is responsible for: (Choose two.)...
Question 181: Which of the following are characteristics of a matrix organ...
Question 182: A project is about to begin the execution phase. The SOW and...
Question 183: A vendor has accepted a proposed project from a customer. Wh...
Question 184: For most organizations, which of the following is the MOST e...
Question 185: Which of the following characteristics would stakeholders MO...
Question 186: Which of the following events would MOST likely merit immedi...
Question 187: The PMO has asked the PM to provide a status report indicati...
Question 188: A change must be made to a project to comply with municipal ...
Question 189: In a projectized organization, a project manager has a need ...
Question 190: When forming a project team, there are a number of phases. W...
Question 191: Which of the following should a project manager consider as ...
Question 192: The government wants to start a project that will launch a s...
Question 193: A project manager is overseeing the construction of a new bu...
Question 194: The Chief Executive Officer (CEO) of a company announced tha...
Question 195: Which of the following includes setting governance gates as ...
Question 196: A project manager at a projectized organization is resource ...
Question 197: Which of the following indicators would help the project man...
Question 198: Which of the following are the roles involved in a Scrum pro...
Question 199: A project scheduler has calculated the project's critical pa...
Question 200: Which of the following defines the minimum level of engageme...
Question 201: Which of the following is a characteristics of a matrix orga...
Question 202: A new project manager is working in an environment where res...
Question 203: A project manager has received a change order that will redu...
Question 204: In a weak matrix, a highly skilled project team member has b...
Question 205: Which of the following shows projected project expenditures?...
Question 206: A project team is creating a new product, and stakeholders a...
Question 207: A program manager informs a project manager that a new, high...
Question 208: An organization has multiple projects that are taking place ...
Question 209: Upper management asks a project sponsor to provide several a...
Question 210: Which of the following documents is typically signed by the ...
Question 211: A project manager is analyzing the cost variances produced w...
Question 212: A project manager detects low performance from a team member...
Question 213: A project manager is starting a project on an unfamiliar tec...
Question 214: A company's Chief Executive Officer (CEO) has asked the proj...
Question 215: Which of the following is the MOST appropriate communication...
Question 216: A project manager is meeting with top management executives ...
Question 217: An audit, project change, task initiation/completion, gate r...
Question 218: Top-level managers are considering joining certain projects,...
Question 219: A project manager is managing a project with a hard deadline...
Question 220: Which of the following inherently affects quality standards?...
Question 221: A project manager wants to introduce the practice of a WBS t...
Question 222: A project manager is managing an eight-month effort and has ...
Question 223: A functional manager pulled a resource from a current projec...
Question 224: The project's network map has a loop with multiple project o...
Question 225: A project requires daily status updates. Which of the follow...
Question 226: Joe, a project team member, was hired after a project was al...
Question 227: A project sponsor no longer wants to receive email communica...
Question 228: In which of the following situations is a project manager MO...
Question 229: A company is hired to perform some of another organization's...
Question 230: There is a project in which the team can only meet once ever...
Question 231: A first-time project manager is developing a project charter...
Question 232: Despite receiving regular updates, a sponsor learns a projec...
Question 233: A project is running behind schedule. To meet the delivery t...
Question 234: A customer will have ongoing changes to project requirements...
Question 235: Which of the following will identify the MOST potential proj...
Question 236: As a project processes, the team appears disjointed. Meeting...
Question 237: A project manager is reviewing a project's status and finds ...
Question 238: Which of the following is the BEST technique for comparing a...
Question 239: During a CCB, a SME evaluated the impact and provided new in...
Question 240: A project manager has contracted a third-party vendor to ach...
Question 241: A sports event is coming to a local city, and the project ma...
Question 242: An active project is focused on quality assurance of the del...
Question 243: Based on the table below: (Exhibit) Which of the following i...
Question 244: Which of the following job roles is MOST responsible for pro...
Question 245: A project team learns that potential remodeling on the produ...
Question 246: A project manager wishes to track a project's performance ag...
Question 247: Project B cannot start before Project A is complete, but Pro...