Which of the following is the reason why liquidated damage clauses are embedded into a contract?
Correct Answer: C
Liquidated damages are an amount of money, agreed upon by the parties at the time of the contract signing, that establishes the damages that can be recovered in the event a party breaches the contract. The amount is supposed to reflect the best estimate of actual damages when the parties sign the contract. These usually apply to a specific type of breach, and in construction, it is frequently the failure to complete work on time.
Liquidated damages clauses are usually written as some sort of formula, for example:
Total Contract Price - [(X amount of $ per day) x (number of days late)] Including a liquidated damages clause can provide many benefits, the most important of which is predictability. When setting a predetermined amount of damages, it allows both parties a chance to negotiate and settle on a number they both feel is fair and reasonable.
From the owner's perspective, this acts like a cheap form of insurance against your contractors. In the event of a breach, the owner can immediately calculate the damages without going through the trouble of proving actual damages. Proving actual damages can be a complicated, lengthy, and costly process.
From a contractor perspective, this allows them to analyze the level of risk involved, and schedule appropriately. It also allows them the opportunity to limit the damage claims of the owner.
Reference:
- Construction Contract Clauses: What Is a Liquidated Damages Clause?
- CIPS study guide page 158-159
LO 3, AC 3.2