An organization has a normal tender process that often last 1 month from defining the needs to contract award. Manufacturing department suddenly required a new special part that they could not foresee within a month. Which of the following should be the priority actions of procurement manager in this urgent situation? Select TWO that apply:
Correct Answer: E
This urgent needs occasionally occur due to a sudden change in circumstances. The process for selecting a replacement supplier must still be controlled. If there is a reason for normal processes to be waived, this must be fully documented and approved at a high level. Reference: CIPS study guide page 7 LO 1, AC 1.1