You are the business analyst for your organization. You are identifying new opportunities to improve upon your existing web services. Management is open to new opportunities as long as the changes do not take more than 60 days to implement. What type of a factor does the 60-day implementation represent?
Correct Answer: B
Explanation/Reference:
A time limit, budget limit, limit on the number of resources, and other organizational restrictions are business constraints.
C is incorrect. A technical constraint describes the architectural decisions concerning hardware,
software, platforms, and interoperability with the enterprise architecture.
D is incorrect. An assumption is something that's believed to be true, but it hasn't yet been proven
to be true.
A is incorrect. A schedule constraint is tempting, but this is not a valid term for business analysis.
Constraints on the time limit are just part of the business constraint.