Valid PK0-004 Dumps shared by ExamDiscuss.com for Helping Passing PK0-004 Exam! ExamDiscuss.com now offer the newest PK0-004 exam dumps, the ExamDiscuss.com PK0-004 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-004 dumps with Test Engine here:

Access PK0-004 Dumps Premium Version
(797 Q&As Dumps, 35%OFF Special Discount Code: freecram)

Online Access Free PK0-004 Exam Questions

Exam Code:PK0-004
Exam Name:CompTIA Project+ Certification Exam
Certification Provider:CompTIA
Free Question Number:288
Version:v2022-10-10
Rating:
# of views:461
# of Questions views:15817
Go To PK0-004 Questions

Recent Comments (The most recent comments are at the top.)

MJVIS - Dec 30, 2022

No.# The project manager wants to escalate the issue to a supervisor. The Organization Chart will show who is the manager of the team member, not a RACI chart.
A RACI chart, also called a RACI matrix, is a type of responsibility assignment matrix (RAM) in project management. In practice, it’s a simple spreadsheet or table that lists all stakeholders on a project and their level of involvement in each task, denoted with the letters R, A, C, or I. Once these roles are defined, assignments can be attributed to the roles and work can begin.

R, A, C, I stand for:

Responsible
Accountable
Consulted
Informed

MJVIS - Dec 30, 2022

No.# Ideally, you should involve your core project team in estimating the duration. You should involve the project team, who will work on the project to achieve the project objectives, the project management team, and all the identified key stakeholders to make a consensus on the milestone dates, and delivery schedules

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Other Version
558 viewsCompTIA.PK0-004.v2022-08-15.q269
537 viewsCompTIA.PK0-004.v2022-05-27.q190
540 viewsCompTIA.PK0-004.v2022-05-20.q247
686 viewsCompTIA.PK0-004.v2022-02-10.q199
1087 viewsCompTIA.PK0-004.v2021-06-21.q176
1389 viewsCompTIA.PK0-004.v2021-01-25.q152
1118 viewsCompTIA.PK0-004.v2020-11-25.q148
1572 viewsCompTIA.PK0-004.v2019-11-07.q100
1408 viewsCompTIA.PK0-004.v2018-11-12.q118
Exam Question List
Question 1: A project team is overseeing the installation of a new repti...
Question 2: A project team added a new member who has proprietary inform...
Question 3: The Chief Executive Officer (CEO) has changed the direction ...
Question 4: An industry leader may be joining the project team and can p...
Question 5: A project stakeholder is disappointed the team was not inclu...
Question 6: Which of the following is the BEST technique for comparing a...
Question 7: Two team members completely disagree on how to complete a sp...
Question 8: A local company is part of a hostile takeover by a multinati...
Question 9: A project manager decides to release a product one month lat...
Question 10: A project facilitator is working within a large project team...
Question 11: A project manager is providing the lessons learned for a pro...
Question 12: A customer-requested project change has been approved, imple...
Question 13: A project team is preparing for a major system upgrade that ...
Question 14: Which of the following statements are correct regarding proj...
Question 15: A hurricane occurs in an area where several key project reso...
Question 16: A project is in the initiation phase. Which of the following...
Question 17: A company is under investigation for monopolization practice...
Question 18: Analogous estimating was used earlier in a hauling project; ...
Question 19: A project manager is assigned a global team. The project man...
Question 20: Two team members approach a project manager with different i...
Question 21: As part of the early stages of a potential corporate acquisi...
Question 22: A project manager chose an architect based on the architect'...
Question 23: The government wants to start a project that will launch a s...
Question 24: An active project has a CPI of 0.92. Which of the following ...
Question 25: A project team is defining detailed risks. Which of the foll...
Question 26: Based on the table below: (Exhibit) Which of the following i...
Question 27: Which of the following is a risk strategy?...
Question 28: Joe, a stakeholder, threatens to withdraw from a project tha...
Question 29: A project sponsor is not being updated on the project as exp...
Question 30: A project manager is overseeing an outsourced team of contra...
1 commentQuestion 31: When developing a project schedule, which of the following r...
Question 32: A customer has requested additional features for an active p...
Question 33: A project team is spread between two countries on different ...
Question 34: While developing a project schedule, the project manager is ...
Question 35: Which of the following will identify the MOST potential proj...
Question 36: A project team has just finished one phase of product develo...
Question 37: Which of the following documents should be used to provide h...
Question 38: The Chief Executive Officer (CEO) informs the project manage...
Question 39: A vendor is late with product deliverables. Which of the fol...
Question 40: A project needs two more months of work to be completed, but...
Question 41: Which of the following includes setting governance gates as ...
Question 42: The supervisor asks an engineer to be a project manager with...
Question 43: A project sponsor has repeatedly indicated dissatisfaction w...
Question 44: Halfway through a project, the project manager is told it ne...
Question 45: A project team has finished creating a WBS and started devel...
Question 46: Prior to engaging a vendor on an RFI, which of the following...
Question 47: A team member has reported Task 3 will be completed ahead of...
Question 48: The project coordinator creates the following list to track ...
1 commentQuestion 49: A new project manager is working in an environment where res...
Question 50: A project manager conducted an audit of project deliverables...
Question 51: A stakeholder with whom the project manager has worked on nu...
Question 52: In a Scrum retrospective, which of the following categories ...
Question 53: A project manager is not required to participate in performa...
Question 54: A project manager learns that a key team member is required ...
Question 55: Which of the following is performed during the monitoring an...
Question 56: A project has fallen behind schedule. Upon investigation, th...
Question 57: The key stakeholders have reported the project pace as being...
Question 58: A first-time project manager is developing a project charter...
Question 59: Before a team can start on a sprint, they will need to:...
Question 60: A project is moving into the next phase, and those involved ...
Question 61: A project manager is reviewing project performance. Which of...
Question 62: A new contractor joining the project team is an example of:...
Question 63: The responsibility of estimating how long a task will take b...
Question 64: A vendor advises the project manager that a key component of...
Question 65: Company A recently partnered with Company B. Over the past f...
Question 66: A newly developed claims processing system will require user...
Question 67: A project team member has completed an assigned task on time...
Question 68: A project sponsor no longer wants to receive email communica...
Question 69: A risk event that was logged in the project risk management ...
Question 70: Which of the following would MOST likely be considered a pro...
Question 71: Which of the following indicators will assist the project ma...
Question 72: A project manager has received a change order that will redu...
Question 73: A project manager was directed to complete a project sooner ...
Question 74: When closing a project, which of the following must be compl...
Question 75: Which of the following describes risk mitigation?...
Question 76: Objectives and tasks are equally assigned by two different m...
Question 77: A project manager is overseeing a multinational project, and...
Question 78: A construction company is building a plant in a territory th...
Question 79: A project manager is creating the WBS. In which of the follo...
Question 80: A politically sensitive project is being proposed. The spons...
Question 81: Which of the following are MOST likely the responsibilities ...
Question 82: Which of the following conflict resolution techniques relies...
Question 83: A diagram or chart is required to illustrate data difference...
Question 84: A financial audit is being performed on a closed project. Wh...
Question 85: When a buyer requests a potential seller to provide details ...
Question 86: The AC plus ETC is known as:
Question 87: A project team is identifying, rating the probability of, an...
Question 88: The project sponsor has cut the resources required for proje...
Question 89: A project manager recently joined a projectized organization...
Question 90: A company engaged a third-party audit firm to provide regula...
Question 91: A project team is executing a transition plan for a project....
Question 92: Which of the following analyses should a project manager use...
Question 93: Which of the following roles is MOST involved in checking th...
Question 94: A project manager is informed that a team member would like ...
Question 95: Because a feature was not meeting documented requirements, a...
Question 96: A project manager is working on the project charter. Which o...
Question 97: A new project manager would benefit from additional assistan...
Question 98: A client has provided a list of deliverables to include in t...
Question 99: New requirements were introduced during the execution phase ...
Question 100: A new stakeholder has requested the status and progress repo...
Question 101: A project team has determined it will need to source data fr...
Question 102: Which of the following charts is a mathematical diagram used...
Question 103: Which of the following project documents should be used to r...
Question 104: A project manager notices several of the action items discus...
Question 105: The project team is distributed throughout a single country....
Question 106: On an OBS chart, there is a dashed line between some team me...
Question 107: A sponsor requests that the project team shorten the complet...
Question 108: Top-level managers are considering joining certain projects,...
Question 109: A project manager is developing a communication plan for an ...
Question 110: While preparing to plan a project, the project manager meets...
Question 111: A project learn is working on a sensitive project that requi...
Question 112: A change must be made to a project to comply with municipal ...
Question 113: The PMO has asked the PM to provide a status report indicati...
Question 114: The upper management team does not agree with certain aspect...
Question 115: Which of the following is primarily responsible for developi...
Question 116: The Chief Executive Officer (CEO) has announced that the har...
Question 117: A post implementation review is being performed as a part of...
Question 118: In which of the following situations is a project manager MO...
Question 119: A recent change request was implemented with approval; howev...
Question 120: A project manager has developed a schedule in which all task...
Question 121: A company was originally organized using a functional struct...
Question 122: A project requires the distribution of training materials fo...
Question 123: A project sponsor informs the project manager that the proje...
Question 124: Language barriers will MOST likely influence a PM to:...
Question 125: As part of a project, employee production cannot proceed unl...
Question 126: Which of the following documents would a project manager uti...
Question 127: A project manager is working on a project, which needs to be...
Question 128: Task A has a duration of 2 days and is a predecessor of task...
Question 129: The project manager was asked to provide recommendations for...
Question 130: Which of the following elements should be included on a resp...
Question 131: Which of the following defines the minimum level of engageme...
Question 132: Which of the following would MOST likely trigger a business ...
Question 133: A stakeholder informs a project manager that a weekly status...
Question 134: A primary work location is unsafe due to a gas leak. The pro...
Question 135: A vendor who is scheduled to arrive in two days encounters a...
Question 136: A project manager needs to identify the resources assigned t...
Question 137: An active project is focused on quality assurance of the del...
Question 138: A PM has notified the project team of an immediate project r...
Question 139: Which of the following primary factors are used to prioritiz...
Question 140: A business has implemented a new online performance manageme...
Question 141: During a risk review session, the project team identified th...
Question 142: A project manager procures additional resources from a local...
Question 143: The stakeholders for an active project requested a change th...
Question 144: An influential stakeholder has left the organization. Which ...
Question 145: An American publisher is participating in a workshop in Hong...
Question 146: A project team is working on a project with high public visi...
Question 147: Which of the following documents should be used FIRST when a...
Question 148: Which of the following documents will provide the MOST detai...
Question 149: Which of the following normally would be completed prior to ...
Question 150: Risk ID 2 has occurred. (Exhibit) Which of the following way...
Question 151: A stakeholder tells the project manager that a vendor was ve...
Question 152: Which of the following represents the order of the team deve...
Question 153: Project status meetings have poor attendance. A SME from the...
Question 154: A project manager identified a risk in a geographically unst...
Question 155: A risk with a high probability and medium consequence to a p...
Question 156: After accepting and assigning a positive risk, risk owners h...
Question 157: The project team is moving from high-level risks to detailed...
Question 158: A firm, fixed-price project is on pace to exceed the maximum...
Question 159: A key stakeholder claims to have not received status updates...
Question 160: A project manager is developing a network diagram to underst...
Question 161: When a project team member completes a task in the WBS, whic...
Question 162: There is friction between team members who were on the team ...
Question 163: A member of a CCB notices a change request was not approved ...
Question 164: A project manager is assigned to a project that was previous...
Question 165: During the initiation phase, a project manager has asked for...
Question 166: A project manager must create documentation before the proje...
Question 167: Which of the following are characteristics of qualitative ri...
Question 168: Which of the following would be captured in a risk register?...
Question 169: A project is coming to the end of a phase. The PMO requires ...
Question 170: A risk with minor impact has been realized. There is no chan...
Question 171: Which of the following documents is typically signed by the ...
Question 172: The project manager for a TV tower construction project rece...
Question 173: A project team started work on a project and was ahead of sc...
Question 174: A vendor notifies the project manager that the scheduled dat...
Question 175: A project team decides to obtain a support contact on one of...
Question 176: Two team members are arguing over two different approaches t...
Question 177: During a project, the project manager realizes some staff po...
Question 178: Two critical members have approached the project manager sep...
Question 179: Which of the following is the BEST reason to conduct regular...
Question 180: A senior manager asks a project manager for an estimated bud...
Question 181: An individual is responsible for the training and education ...
Question 182: Ann. a project sponsor, is concerned by how long issues rema...
Question 183: A new project has just commenced. Project team members are c...
Question 184: After identifying all known tasks, the project manager has s...
Question 185: Two companies have merged. Which of the following may impact...
Question 186: A project manager has noticed poor attendance as status meet...
Question 187: In which of the following categories does a business process...
Question 188: While working on a project, a self-organized team determines...
Question 189: A company's finance director asks the PMO for help gathering...
Question 190: An external consultant reviews benchmark staffing for an org...
Question 191: A new stakeholder has joined the project team and requested ...
Question 192: A project, which is nearing completion, is ahead of schedule...
Question 193: A key stakeholder asks the project manager for additional fe...
Question 194: A Chief Executive Officer (CEO) has approached a project tea...
Question 195: To maintain an active project's progress, the project manage...
Question 196: A project manager in a small organization wants to improve e...
Question 197: A customer has stated that meeting the project schedule and ...
Question 198: A project manager has received numerous complaints from staf...
Question 199: To control costs, project funding is being released under a ...
Question 200: Ann, a project manager, is working for a new company. On her...
Question 201: Project team members have stated that they are having diffic...
Question 202: Which of the following measurements would give the project m...
Question 203: A new project manager is taking over a project that is alrea...
Question 204: A project team is mainly based in a metropolitan are a. The ...
Question 205: The following tasks are required to complete an IT project t...
Question 206: A company has updated the method it uses to initiate project...
Question 207: The senior management team decides to open a branch in a new...
Question 208: Which of the following documents will MOST likely result in ...
Question 209: A team member was replaced on a project by a new team member...
Question 210: A contract manager is reconciling project invoices and needs...
Question 211: A resource is assigned to two projects with two scheduled ta...
Question 212: Which of the following are mutually binding project document...
Question 213: In a multinational project, the project manager notices team...
Question 214: A program manager asks for a visual representation of tasks,...
Question 215: Collaboration tools are BEST used instead of email when mult...
Question 216: Task B is not planned to start until Task A is completed. Ta...
Question 217: Upper management asks a project sponsor to provide several a...
Question 218: A meeting organizer is deciding high-level requirements, the...
Question 219: Which of the following activity sequencing techniques uses n...
Question 220: A company just announced all third-party vendors must provid...
Question 221: Based on the table below: (Exhibit) Which of the following i...
Question 222: Which of the following describes a project's budget overrun?...
Question 223: A project manager has set aside a contingency reserve for un...
Question 224: When developing a project schedule, which of the following t...
Question 225: Some resources are waiting to be assigned to a new project. ...
Question 226: A project manager does not have enough time to complete seve...
Question 227: A project sponsor promises the Chief Executive Officer (CEO)...
Question 228: Which of the following documents focus primarily on support ...
Question 229: A project manager holds weekly project status meetings with ...
Question 230: A project team member highlights to the project manager that...
Question 231: A project manager is attempting to establish the proper sequ...
Question 232: During a project, there has been a high turnover of resource...
Question 233: A company has been trying to implement a product with multip...
Question 234: A manufacturer is developing a product that will start in on...
Question 235: A highly skilled, key project team member lacks technical wr...
Question 236: A project manager has taken over a project that is already i...
Question 237: While creating the communication management plan, the projec...
Question 238: When a risk event occurs, which of the following documents i...
Question 239: Project cost control deals with:...
Question 240: Tasks A and B have a duration of two days. Task A starts on ...
Question 241: A project manager is managing a project with a hard deadline...
Question 242: During an active project, the finished deliverables become s...
Question 243: While planning a project, the project team estimates known e...
Question 244: In a projectized organization, a project manager has a need ...
Question 245: The project manager is reviewing the earned value of work co...
Question 246: A cost baseline is used to measure the:...
Question 247: The president of a company is pushing to get a product on th...
Question 248: Which of the following is the MOST likely trigger to update ...
Question 249: A client has requested a project be completed ahead of sched...
Question 250: A company has hired a new project manager. The PMO has brief...
Question 251: The project team has identified all the tasks needed to crea...
Question 252: A team member has completed an assigned task. Which of the f...
Question 253: A quality auditor finds suspicious code during a software te...
Question 254: A new project manager was hired to help transition projects ...
Question 255: A customer has requested a new feature be included in the ne...
Question 256: During the execution phase of a project, a project task has ...
Question 257: A project sponsor, project manager, and project facilitator ...
Question 258: A project is nearing the expected completion date, but it is...
Question 259: A project coordinator holds a status meeting about a new pro...
Question 260: A PM receives notification that an issue will impact a deliv...
Question 261: A project manager has updated the project schedule but canno...
Question 262: A company accepts a proposal from a third-party vendor to pr...
Question 263: As a project processes, the team appears disjointed. Meeting...
Question 264: A project is approaching its end when the project manager is...
Question 265: A customer is in the early planning stages of a technology r...
Question 266: A project manager is reviewing documents to develop the proj...
Question 267: To resolve a dispute between two project team members, the p...
Question 268: Which of the following should receive regular communication ...
Question 269: A company is about to initiate a cybersecurity project. Howe...
Question 270: A vendor is not meeting the agreed-upon quality of deliverab...
Question 271: A team member has completed a project task. Which of the fol...
Question 272: Which of the following job roles is primarily tasked with co...
Question 273: A manager is reviewing some projects with two project manage...
Question 274: A team lead informs the project manager that the datacenter ...
Question 275: A project manager notices a lack of meeting attendance from ...
Question 276: A sensitive project requires activities to occur with very s...
Question 277: A new project sponsor has joined the project team, and the c...
Question 278: A company's management team is in a meeting to review all th...
Question 279: A governance committee has just approved a new project. The ...
Question 280: A project manager is notified of a natural disaster that may...
Question 281: Which of the following techniques modifies the schedule base...
Question 282: A PM is asked to keep the Chief Information Officer (CIO) in...
Question 283: A project manager needs to track the actual and estimated st...
Question 284: A project scheduler has calculated the project's critical pa...
Question 285: Which of the following metrics demonstrates to a project man...
Question 286: After SOW and contract approvals, the project manager plans ...
Question 287: A project team has purchased computers with warranties exten...
Question 288: Joe, a project team member, was hired after a project was al...