<< Prev Question Next Question >>

Question 284/288

A project scheduler has calculated the project's critical path. Which of the following activities would most likely occur NEXT?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (288q)
Question 1: A project team is overseeing the installation of a new repti...
Question 2: A project team added a new member who has proprietary inform...
Question 3: The Chief Executive Officer (CEO) has changed the direction ...
Question 4: An industry leader may be joining the project team and can p...
Question 5: A project stakeholder is disappointed the team was not inclu...
Question 6: Which of the following is the BEST technique for comparing a...
Question 7: Two team members completely disagree on how to complete a sp...
Question 8: A local company is part of a hostile takeover by a multinati...
Question 9: A project manager decides to release a product one month lat...
Question 10: A project facilitator is working within a large project team...
Question 11: A project manager is providing the lessons learned for a pro...
Question 12: A customer-requested project change has been approved, imple...
Question 13: A project team is preparing for a major system upgrade that ...
Question 14: Which of the following statements are correct regarding proj...
Question 15: A hurricane occurs in an area where several key project reso...
Question 16: A project is in the initiation phase. Which of the following...
Question 17: A company is under investigation for monopolization practice...
Question 18: Analogous estimating was used earlier in a hauling project; ...
Question 19: A project manager is assigned a global team. The project man...
Question 20: Two team members approach a project manager with different i...
Question 21: As part of the early stages of a potential corporate acquisi...
Question 22: A project manager chose an architect based on the architect'...
Question 23: The government wants to start a project that will launch a s...
Question 24: An active project has a CPI of 0.92. Which of the following ...
Question 25: A project team is defining detailed risks. Which of the foll...
Question 26: Based on the table below: (Exhibit) Which of the following i...
Question 27: Which of the following is a risk strategy?...
Question 28: Joe, a stakeholder, threatens to withdraw from a project tha...
Question 29: A project sponsor is not being updated on the project as exp...
Question 30: A project manager is overseeing an outsourced team of contra...
1 commentQuestion 31: When developing a project schedule, which of the following r...
Question 32: A customer has requested additional features for an active p...
Question 33: A project team is spread between two countries on different ...
Question 34: While developing a project schedule, the project manager is ...
Question 35: Which of the following will identify the MOST potential proj...
Question 36: A project team has just finished one phase of product develo...
Question 37: Which of the following documents should be used to provide h...
Question 38: The Chief Executive Officer (CEO) informs the project manage...
Question 39: A vendor is late with product deliverables. Which of the fol...
Question 40: A project needs two more months of work to be completed, but...
Question 41: Which of the following includes setting governance gates as ...
Question 42: The supervisor asks an engineer to be a project manager with...
Question 43: A project sponsor has repeatedly indicated dissatisfaction w...
Question 44: Halfway through a project, the project manager is told it ne...
Question 45: A project team has finished creating a WBS and started devel...
Question 46: Prior to engaging a vendor on an RFI, which of the following...
Question 47: A team member has reported Task 3 will be completed ahead of...
Question 48: The project coordinator creates the following list to track ...
1 commentQuestion 49: A new project manager is working in an environment where res...
Question 50: A project manager conducted an audit of project deliverables...
Question 51: A stakeholder with whom the project manager has worked on nu...
Question 52: In a Scrum retrospective, which of the following categories ...
Question 53: A project manager is not required to participate in performa...
Question 54: A project manager learns that a key team member is required ...
Question 55: Which of the following is performed during the monitoring an...
Question 56: A project has fallen behind schedule. Upon investigation, th...
Question 57: The key stakeholders have reported the project pace as being...
Question 58: A first-time project manager is developing a project charter...
Question 59: Before a team can start on a sprint, they will need to:...
Question 60: A project is moving into the next phase, and those involved ...
Question 61: A project manager is reviewing project performance. Which of...
Question 62: A new contractor joining the project team is an example of:...
Question 63: The responsibility of estimating how long a task will take b...
Question 64: A vendor advises the project manager that a key component of...
Question 65: Company A recently partnered with Company B. Over the past f...
Question 66: A newly developed claims processing system will require user...
Question 67: A project team member has completed an assigned task on time...
Question 68: A project sponsor no longer wants to receive email communica...
Question 69: A risk event that was logged in the project risk management ...
Question 70: Which of the following would MOST likely be considered a pro...
Question 71: Which of the following indicators will assist the project ma...
Question 72: A project manager has received a change order that will redu...
Question 73: A project manager was directed to complete a project sooner ...
Question 74: When closing a project, which of the following must be compl...
Question 75: Which of the following describes risk mitigation?...
Question 76: Objectives and tasks are equally assigned by two different m...
Question 77: A project manager is overseeing a multinational project, and...
Question 78: A construction company is building a plant in a territory th...
Question 79: A project manager is creating the WBS. In which of the follo...
Question 80: A politically sensitive project is being proposed. The spons...
Question 81: Which of the following are MOST likely the responsibilities ...
Question 82: Which of the following conflict resolution techniques relies...
Question 83: A diagram or chart is required to illustrate data difference...
Question 84: A financial audit is being performed on a closed project. Wh...
Question 85: When a buyer requests a potential seller to provide details ...
Question 86: The AC plus ETC is known as:
Question 87: A project team is identifying, rating the probability of, an...
Question 88: The project sponsor has cut the resources required for proje...
Question 89: A project manager recently joined a projectized organization...
Question 90: A company engaged a third-party audit firm to provide regula...
Question 91: A project team is executing a transition plan for a project....
Question 92: Which of the following analyses should a project manager use...
Question 93: Which of the following roles is MOST involved in checking th...
Question 94: A project manager is informed that a team member would like ...
Question 95: Because a feature was not meeting documented requirements, a...
Question 96: A project manager is working on the project charter. Which o...
Question 97: A new project manager would benefit from additional assistan...
Question 98: A client has provided a list of deliverables to include in t...
Question 99: New requirements were introduced during the execution phase ...
Question 100: A new stakeholder has requested the status and progress repo...
Question 101: A project team has determined it will need to source data fr...
Question 102: Which of the following charts is a mathematical diagram used...
Question 103: Which of the following project documents should be used to r...
Question 104: A project manager notices several of the action items discus...
Question 105: The project team is distributed throughout a single country....
Question 106: On an OBS chart, there is a dashed line between some team me...
Question 107: A sponsor requests that the project team shorten the complet...
Question 108: Top-level managers are considering joining certain projects,...
Question 109: A project manager is developing a communication plan for an ...
Question 110: While preparing to plan a project, the project manager meets...
Question 111: A project learn is working on a sensitive project that requi...
Question 112: A change must be made to a project to comply with municipal ...
Question 113: The PMO has asked the PM to provide a status report indicati...
Question 114: The upper management team does not agree with certain aspect...
Question 115: Which of the following is primarily responsible for developi...
Question 116: The Chief Executive Officer (CEO) has announced that the har...
Question 117: A post implementation review is being performed as a part of...
Question 118: In which of the following situations is a project manager MO...
Question 119: A recent change request was implemented with approval; howev...
Question 120: A project manager has developed a schedule in which all task...
Question 121: A company was originally organized using a functional struct...
Question 122: A project requires the distribution of training materials fo...
Question 123: A project sponsor informs the project manager that the proje...
Question 124: Language barriers will MOST likely influence a PM to:...
Question 125: As part of a project, employee production cannot proceed unl...
Question 126: Which of the following documents would a project manager uti...
Question 127: A project manager is working on a project, which needs to be...
Question 128: Task A has a duration of 2 days and is a predecessor of task...
Question 129: The project manager was asked to provide recommendations for...
Question 130: Which of the following elements should be included on a resp...
Question 131: Which of the following defines the minimum level of engageme...
Question 132: Which of the following would MOST likely trigger a business ...
Question 133: A stakeholder informs a project manager that a weekly status...
Question 134: A primary work location is unsafe due to a gas leak. The pro...
Question 135: A vendor who is scheduled to arrive in two days encounters a...
Question 136: A project manager needs to identify the resources assigned t...
Question 137: An active project is focused on quality assurance of the del...
Question 138: A PM has notified the project team of an immediate project r...
Question 139: Which of the following primary factors are used to prioritiz...
Question 140: A business has implemented a new online performance manageme...
Question 141: During a risk review session, the project team identified th...
Question 142: A project manager procures additional resources from a local...
Question 143: The stakeholders for an active project requested a change th...
Question 144: An influential stakeholder has left the organization. Which ...
Question 145: An American publisher is participating in a workshop in Hong...
Question 146: A project team is working on a project with high public visi...
Question 147: Which of the following documents should be used FIRST when a...
Question 148: Which of the following documents will provide the MOST detai...
Question 149: Which of the following normally would be completed prior to ...
Question 150: Risk ID 2 has occurred. (Exhibit) Which of the following way...
Question 151: A stakeholder tells the project manager that a vendor was ve...
Question 152: Which of the following represents the order of the team deve...
Question 153: Project status meetings have poor attendance. A SME from the...
Question 154: A project manager identified a risk in a geographically unst...
Question 155: A risk with a high probability and medium consequence to a p...
Question 156: After accepting and assigning a positive risk, risk owners h...
Question 157: The project team is moving from high-level risks to detailed...
Question 158: A firm, fixed-price project is on pace to exceed the maximum...
Question 159: A key stakeholder claims to have not received status updates...
Question 160: A project manager is developing a network diagram to underst...
Question 161: When a project team member completes a task in the WBS, whic...
Question 162: There is friction between team members who were on the team ...
Question 163: A member of a CCB notices a change request was not approved ...
Question 164: A project manager is assigned to a project that was previous...
Question 165: During the initiation phase, a project manager has asked for...
Question 166: A project manager must create documentation before the proje...
Question 167: Which of the following are characteristics of qualitative ri...
Question 168: Which of the following would be captured in a risk register?...
Question 169: A project is coming to the end of a phase. The PMO requires ...
Question 170: A risk with minor impact has been realized. There is no chan...
Question 171: Which of the following documents is typically signed by the ...
Question 172: The project manager for a TV tower construction project rece...
Question 173: A project team started work on a project and was ahead of sc...
Question 174: A vendor notifies the project manager that the scheduled dat...
Question 175: A project team decides to obtain a support contact on one of...
Question 176: Two team members are arguing over two different approaches t...
Question 177: During a project, the project manager realizes some staff po...
Question 178: Two critical members have approached the project manager sep...
Question 179: Which of the following is the BEST reason to conduct regular...
Question 180: A senior manager asks a project manager for an estimated bud...
Question 181: An individual is responsible for the training and education ...
Question 182: Ann. a project sponsor, is concerned by how long issues rema...
Question 183: A new project has just commenced. Project team members are c...
Question 184: After identifying all known tasks, the project manager has s...
Question 185: Two companies have merged. Which of the following may impact...
Question 186: A project manager has noticed poor attendance as status meet...
Question 187: In which of the following categories does a business process...
Question 188: While working on a project, a self-organized team determines...
Question 189: A company's finance director asks the PMO for help gathering...
Question 190: An external consultant reviews benchmark staffing for an org...
Question 191: A new stakeholder has joined the project team and requested ...
Question 192: A project, which is nearing completion, is ahead of schedule...
Question 193: A key stakeholder asks the project manager for additional fe...
Question 194: A Chief Executive Officer (CEO) has approached a project tea...
Question 195: To maintain an active project's progress, the project manage...
Question 196: A project manager in a small organization wants to improve e...
Question 197: A customer has stated that meeting the project schedule and ...
Question 198: A project manager has received numerous complaints from staf...
Question 199: To control costs, project funding is being released under a ...
Question 200: Ann, a project manager, is working for a new company. On her...
Question 201: Project team members have stated that they are having diffic...
Question 202: Which of the following measurements would give the project m...
Question 203: A new project manager is taking over a project that is alrea...
Question 204: A project team is mainly based in a metropolitan are a. The ...
Question 205: The following tasks are required to complete an IT project t...
Question 206: A company has updated the method it uses to initiate project...
Question 207: The senior management team decides to open a branch in a new...
Question 208: Which of the following documents will MOST likely result in ...
Question 209: A team member was replaced on a project by a new team member...
Question 210: A contract manager is reconciling project invoices and needs...
Question 211: A resource is assigned to two projects with two scheduled ta...
Question 212: Which of the following are mutually binding project document...
Question 213: In a multinational project, the project manager notices team...
Question 214: A program manager asks for a visual representation of tasks,...
Question 215: Collaboration tools are BEST used instead of email when mult...
Question 216: Task B is not planned to start until Task A is completed. Ta...
Question 217: Upper management asks a project sponsor to provide several a...
Question 218: A meeting organizer is deciding high-level requirements, the...
Question 219: Which of the following activity sequencing techniques uses n...
Question 220: A company just announced all third-party vendors must provid...
Question 221: Based on the table below: (Exhibit) Which of the following i...
Question 222: Which of the following describes a project's budget overrun?...
Question 223: A project manager has set aside a contingency reserve for un...
Question 224: When developing a project schedule, which of the following t...
Question 225: Some resources are waiting to be assigned to a new project. ...
Question 226: A project manager does not have enough time to complete seve...
Question 227: A project sponsor promises the Chief Executive Officer (CEO)...
Question 228: Which of the following documents focus primarily on support ...
Question 229: A project manager holds weekly project status meetings with ...
Question 230: A project team member highlights to the project manager that...
Question 231: A project manager is attempting to establish the proper sequ...
Question 232: During a project, there has been a high turnover of resource...
Question 233: A company has been trying to implement a product with multip...
Question 234: A manufacturer is developing a product that will start in on...
Question 235: A highly skilled, key project team member lacks technical wr...
Question 236: A project manager has taken over a project that is already i...
Question 237: While creating the communication management plan, the projec...
Question 238: When a risk event occurs, which of the following documents i...
Question 239: Project cost control deals with:...
Question 240: Tasks A and B have a duration of two days. Task A starts on ...
Question 241: A project manager is managing a project with a hard deadline...
Question 242: During an active project, the finished deliverables become s...
Question 243: While planning a project, the project team estimates known e...
Question 244: In a projectized organization, a project manager has a need ...
Question 245: The project manager is reviewing the earned value of work co...
Question 246: A cost baseline is used to measure the:...
Question 247: The president of a company is pushing to get a product on th...
Question 248: Which of the following is the MOST likely trigger to update ...
Question 249: A client has requested a project be completed ahead of sched...
Question 250: A company has hired a new project manager. The PMO has brief...
Question 251: The project team has identified all the tasks needed to crea...
Question 252: A team member has completed an assigned task. Which of the f...
Question 253: A quality auditor finds suspicious code during a software te...
Question 254: A new project manager was hired to help transition projects ...
Question 255: A customer has requested a new feature be included in the ne...
Question 256: During the execution phase of a project, a project task has ...
Question 257: A project sponsor, project manager, and project facilitator ...
Question 258: A project is nearing the expected completion date, but it is...
Question 259: A project coordinator holds a status meeting about a new pro...
Question 260: A PM receives notification that an issue will impact a deliv...
Question 261: A project manager has updated the project schedule but canno...
Question 262: A company accepts a proposal from a third-party vendor to pr...
Question 263: As a project processes, the team appears disjointed. Meeting...
Question 264: A project is approaching its end when the project manager is...
Question 265: A customer is in the early planning stages of a technology r...
Question 266: A project manager is reviewing documents to develop the proj...
Question 267: To resolve a dispute between two project team members, the p...
Question 268: Which of the following should receive regular communication ...
Question 269: A company is about to initiate a cybersecurity project. Howe...
Question 270: A vendor is not meeting the agreed-upon quality of deliverab...
Question 271: A team member has completed a project task. Which of the fol...
Question 272: Which of the following job roles is primarily tasked with co...
Question 273: A manager is reviewing some projects with two project manage...
Question 274: A team lead informs the project manager that the datacenter ...
Question 275: A project manager notices a lack of meeting attendance from ...
Question 276: A sensitive project requires activities to occur with very s...
Question 277: A new project sponsor has joined the project team, and the c...
Question 278: A company's management team is in a meeting to review all th...
Question 279: A governance committee has just approved a new project. The ...
Question 280: A project manager is notified of a natural disaster that may...
Question 281: Which of the following techniques modifies the schedule base...
Question 282: A PM is asked to keep the Chief Information Officer (CIO) in...
Question 283: A project manager needs to track the actual and estimated st...
Question 284: A project scheduler has calculated the project's critical pa...
Question 285: Which of the following metrics demonstrates to a project man...
Question 286: After SOW and contract approvals, the project manager plans ...
Question 287: A project team has purchased computers with warranties exten...
Question 288: Joe, a project team member, was hired after a project was al...