Valid LEED-Green-Associate Dumps shared by ExamDiscuss.com for Helping Passing LEED-Green-Associate Exam! ExamDiscuss.com now offer the newest LEED-Green-Associate exam dumps, the ExamDiscuss.com LEED-Green-Associate exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com LEED-Green-Associate dumps with Test Engine here:
The amount of landfill-destined waste generated during project construction can be reduced by requiring the general contractor to
Correct Answer: C
Explanation The amount of landfill-destined waste generated during project construction can be reduced by requiring the general contractor to follow requirements for using dimensional construction materials, prefabrication or material efficient framing. These methods reduce the amount of material waste by minimizing cutting, fitting, and trimming on site, and by using standardized or modular components that can be easily reused or recycled. The LEED Green Associate Candidate Handbook states that one of the strategies for achieving materials and resources efficiency is to "reduce construction waste through efficient framing techniques" [1, p. 15]. References: LEED Green Associate Candidate Handbook, [Reducing Construction Waste | U.S. Environmental Protection Agency]