Valid SAFe-POPM Dumps shared by ExamDiscuss.com for Helping Passing SAFe-POPM Exam! ExamDiscuss.com now offer the newest SAFe-POPM exam dumps, the ExamDiscuss.com SAFe-POPM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com SAFe-POPM dumps with Test Engine here:
Which is developed by teams and rolled up to the ART level during PI Planning?
Correct Answer: C
Explanation Objectives are developed by teams and rolled up to the ART level during PI Planning. Objectives are a summary of the business and technical goals that the teams and the ART intend to achieve in the upcoming Program Increment (PI)1. During PI Planning, each team creates their own team PI objectives, which are then presented and reviewed by the ART and the stakeholders2. The aggregated team PI objectives form the ART PI objectives, which provide a common vision and alignment for the ART3. References: *PI Objectives - Scaled Agile Framework *PI Planning - Scaled Agile Framework