If there are multiple Scrum Teams working on the same product, all of the Scrum Teams must mutually define a Definition of Ready (DoR). The DoR is a checklist that the Product Owner must fulfill before a Product Backlog item can be presented at the Sprint Planning. This protects the Development Team from interruptions and disruptions during the Sprint.
Correct Answer: B
Explanation
Explanation:
Product Backlog items should be clear enough and have enough information for the Product Owner and Development to understand the work that needs to be done and to create a forecast of Product Backlog items to implement the Sprint Goal. Nothing stops the flow of Sprints, for example, we do not delay the Sprint because the items are not ready. In such cases, the "unready" items would be selected for the Sprint anyway and refined during the Sprint.
In the case that the Product Backlog items are not clear enough, the Development Team forecasts the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint. At the end of the Sprint, the Scrum Team can discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.