Valid PSM-II Dumps shared by ExamDiscuss.com for Helping Passing PSM-II Exam! ExamDiscuss.com now offer the newest PSM-II exam dumps, the ExamDiscuss.com PSM-II exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PSM-II dumps with Test Engine here:
A new member has just joined an existing Development Team that has been together for several Sprints. During the Sprint, the individual has been trying to share his ideas and viewpoints but is continuously ignored by the rest of the Development Team. Which three Scrum Values has the Development Team been neglecting? (Choose three.)
Correct Answer: B,E,F
The Scrum Team members have courage to do the right thing and work on challenging problems. The Scrum Team agree to be open (to speak and listen) about all the work and the challenges with performing the work. Scrum Team members respect each other's skills, experience, and opinions.