Valid PSM-I Dumps shared by ExamDiscuss.com for Helping Passing PSM-I Exam! ExamDiscuss.com now offer the newest PSM-I exam dumps, the ExamDiscuss.com PSM-I exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PSM-I dumps with Test Engine here:
The correct answer is A, because the Scrum Guide states that "a Sprint can be cancelled before the Sprint time-box is over. Only the Product Owner has the authority to cancel the Sprint, although he or she may do so under influence from the stakeholders, the Development Team, or the Scrum Master." Therefore, a Development Team cannot cancel a Sprint by itself.