What is the recommended size for a Development Team?
Correct Answer: D
The correct answer is D, because the recommended size for a Development Team is 3 to 9 members. The Scrum Guide states that "fewer than three Development Team members decrease interaction and results in smaller productivity gains. Smaller Development Teams may encounter skill constraints during the Sprint, causing the Development Team to be unable to deliver a potentially releasable Increment. Having more than nine members requires too much coordination. Large Development Teams generate too much complexity for an empirical process to be useful."