he correct answer is A, because doing all work needed to meet the definition of "Done" enhances the transparency of an increment. The Scrum Guide states that "when a Product Backlog item or an Increment is described as 'Done', everyone must understand what 'Done' means." Therefore, by meeting the definition of "Done", an increment becomes transparent to all stakeholders and ready for release.