Question 43/132

As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?
(choose the best two answers)

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (132q)
Question 1: When does the second Sprint start?...
Question 2: When is a Product Backlog item considered complete? (choose ...
Question 3: Which two things should the Development Team do during the f...
Question 4: What are two responsibilities of testers in a Scrum Team? (c...
Question 5: (What should the Scrum Team do during the first Sprint? Choo...
Question 6: Who should make sure everyone on the Development Team does t...
Question 7: Which of the following are roles on a Scrum Team? (Choose al...
Question 8: Which of the following services are appropriate for a Scrum ...
Question 9: When multiple Scrum Teams are working on the same product, s...
Question 10: A Product Owner wants advice from the Scrum Master about est...
Question 11: The CEO asks the Development Team to add a "very important" ...
Question 12: The Scrum Master observes the Product Owner struggling with ...
Question 13: As the Sprint Planning meeting progresses, the Development T...
Question 14: Which two things should the Scrum Team do during the first S...
Question 15: (What is the Product Owner responsible for during the Sprint...
Question 16: Which are appropriate topics for discussion in a Sprint Retr...
Question 17: (Which of the following are the Developers accountable for? ...
Question 18: A Scrum Master is keeping a list of open impediments, but it...
Question 19: A Sprint Retrospective should be held:...
Question 20: When must a Product Owner release each Increment? (Choose th...
Question 21: You are the Scrum Master on a newly formed Scrum Team. Which...
Question 22: In accordance with Scrum theory, how should a group of 100 p...
Question 23: Which two things are appropriate for a Scrum Master to do if...
Question 24: (What is the Scrum Master responsible for during the Sprint ...
Question 25: Who can abnormally terminate a Sprint?...
Question 26: During a Sprint, when is new work or further decomposition o...
Question 27: A new Developer is having continuing conflicts with existing...
Question 28: Which topics should be discussed in the Sprint Review? (Choo...
Question 29: In the Sprint Planning meeting, the Product Owner and the De...
Question 30: A Scrum Team is only allowed to meet with stakeholders durin...
Question 31: What is the purpose of a Sprint Review?...
Question 32: (What are the two primary ways a Scrum Master helps a Scrum ...
Question 33: When does the next Sprint begin?...
Question 34: Which of these may a Scrum Team deliver at the end of a Spri...
Question 35: What are two ways that regulatory compliance issues are deal...
Question 36: What are three ways Scrum promotes self-management?...
Question 37: What is the tactic a Scrum Master should use to divide a gro...
Question 38: What are two good ways for a Scrum Team to ensure security c...
Question 39: Which does a self-organizing Development Team choose?...
Question 40: True or False: A scrum Master Fulfills me same role as a tra...
Question 41: (What are two ways that regulatory compliance requirements a...
Question 42: Which statement best describes Scrum? (choose the best answe...
Question 43: As the Sprint Planning progresses, the Developers realize th...
Question 44: A Scrum Master is working with a Development Team that has m...
Question 45: Who is responsible for the Sprint Backlog? (choose the best ...
Question 46: The Daily Scrum is an event that happens every day. What wou...
Question 47: When is a Sprint over?
Question 48: User documentation is part of your definition of "Done". How...
Question 49: Which two things should the Development Team do during the f...
Question 50: What is the best suited structure for Development Teams in o...
Question 51: You are the Scrum Master for four Scrum Teams working from t...
Question 52: What techniques could the Scrum Master use when the Scrum Te...
Question 53: Every Development Team should have:...
Question 54: True or False: The Sprint Backlog is a result of Sprint Plan...
Question 55: Which two things are appropriate for a Scrum Master to do, i...
Question 56: What are the two primary ways a Scrum Master keeps a Develop...
Question 57: The IT manager asks a Development Team for a status report d...
Question 58: Who does the work to make sure Product Backlog items conform...
Question 59: Scrum has a role called "Project Manager"....
Question 60: If burndown charts are used to visualize progress, what do t...
Question 61: What enhances the transparency of an increment?...
Question 62: Who is responsible for the sizing of Product Backlog items? ...
Question 63: How should Product Backlog items be chosen when multiple Scr...
Question 64: What is the time-box for the Sprint Planning meeting?...
Question 65: Which of the following is a Developer accountable for? (Choo...
Question 66: What does it mean for a Development Team to be cross-functio...
Question 67: A Development Team selects a set of Product Backlog items fo...
Question 68: A Scrum Master is introducing Scrum to a new Development Tea...
Question 69: (How is management that is external to the Scrum Team involv...
Question 70: True or False A scrum Master fulfills the same role as a tra...
Question 71: Which approach is best for Scrum Teams in order to produce v...
Question 72: Which statement best describes a Product Owner's responsibil...
Question 73: (True or False: Cross-functional teams are optimized to work...
Question 74: Which answer best describes the topics covered in Sprint Pla...
Question 75: (Who should make sure everyone on the Scrum Team does their ...
Question 76: At the end of a Sprint Product Backlog item worked on during...
Question 77: When a Development Team is having trouble delivering a worki...
Question 78: Which are NOT appropriate topics for discussion in a Sprint ...
Question 79: Which of the following is required by Scrum? (Choose all tha...
Question 80: What does it mean for a Scrum Team to be cross-functional? (...
Question 81: You have just been hired by a company new to Scrum. Your man...
Question 82: Which Scrum Values are exhibited by not building Product Bac...
Question 83: Currently, your Development Teams are organized to address a...
Question 84: Cross-functional teams are optimized to work on one technica...
Question 85: (A Developer takes the Scrum Master aside to express concern...
Question 86: One of the Scrum events is the Daily Scrum. What are two int...
Question 87: User documentation is part of your Definition of Done. Howev...
Question 88: A Scrum Team is required to deliver a done Increment by the ...
Question 89: True or False Developers do not meet with stakeholders: only...
Question 90: What is the role of management in Scrum?...
Question 91: True or False: An increment must be released to customers or...
Question 92: Which answer best describes the topics covered in Sprint Pla...
Question 93: When is implementation of a Product Backlog item considered ...
Question 94: When is it most appropriate for a Scrum Team to change the d...
Question 95: (The Definition of Done serves which three purposes? Choose ...
Question 96: Which two activities will a Product Owner engage in during a...
Question 97: Who is responsible for managing the progress of work during ...
Question 98: What are three benefits of self-organization? (Choose three....
Question 99: Why does the Product Owner want the Development Team to adhe...
Question 100: Who creates a Product Backlog Item's estimate?...
Question 101: When must the Product Owner participate in the Dairy Scrum? ...
Question 102: Every Scrum team must have a Product Owner and Scrum Master....
Question 103: Which three of the following are time-boxed events in Scrum?...
Question 104: Who should know the most about the progress toward a busines...
Question 105: A Development Team asks their Product Owner to re-order the ...
Question 106: As the Development Team starts work during the Sprint, it re...
Question 107: The Sprint Review is mainly an inspect and adapt opportunity...
Question 108: A Sprint Retrospective should be held:...
Question 109: How do you know that a Development Team is cross-functional?...
Question 110: When multiple Scrum Teams are working on a single product, w...
Question 111: (The Developers ask their Product Owner to re-order the Prod...
Question 112: Which three of the following are time-boxed events in Scrum?...
Question 113: When multiple Scrum Teams are working on a single product, w...
Question 114: Why should the Product Owner be present at the Daily Scrum?...
Question 115: (Who must attend the Daily Scrum? Choose the best answer.)...
Question 116: Who determines when it is appropriate to update the Sprint B...
Question 117: A Scrum Team is a cohesive unit of professionals that consis...
Question 118: What two techniques could the Scrum Master use when the Scru...
Question 119: What are two ways that architecture and infrastructure are h...
Question 120: When many Development Teams are working on a single product,...
Question 121: How is management external to the Scrum Team involved in the...
Question 122: Which are properties of the Daily Scrum? (Choose two.)...
Question 123: For the purpose of transparency, when does Scrum say a new i...
Question 124: Who owns the Sprint Backlog?
Question 125: Which two of the following are appropriate topics for discus...
Question 126: A Scrum Master is introducing Scrum to a new Team. The Team ...
Question 127: Which statement best describes the Sprint Backlog as outcome...
Question 128: What does it mean to say that an event has a time-box?...
Question 129: Multiple Scrum Teams working on the same project must have t...
Question 130: What is included in the Sprint Backlog?...
Question 131: What are three ways Scrum promotes self-organization? (Choos...
Question 132: Which statement best describes Scrum?...