Which of the following metrics are likely to be reviewed during flow-based Daily Scrum? (choose the best two answers)
Correct Answer: A,B
During a flow-based Daily Scrum, the team is likely to review metrics such as Work Item Age and Work in Progress (WIP): *Work Item Age: Helps to identify items that have been in progress for a longer time than expected, signaling possible impediments or the need for swarming to complete those items. *Work in Progress (WIP): Indicates the number of items currently being worked on, ensuring that the team is not exceeding the agreed WIP limits, which is crucial for maintaining a steady flow