What might be considered during the Sprint Retrospective once a team decides to supplement their Scrum with Kanban?
(choose the best answer)
Correct Answer: E
During the Sprint Retrospective, once a team decides to supplement their Scrum with Kanban, all the mentioned elements might be considered:
*Workflow: To ensure it aligns with Kanban practices.
*Current policies: To review and adapt any team policies that may need to change.
*WIP Limit: To set appropriate limits to enhance flow.
*Metrics and charts (e.g., Cumulative Flow Diagram, Cycle Time Scatterplot, Work Item Aging): To visualize flow, identify bottlenecks, and make data-driven decisions for continuous improvement.
Considering all these elements helps the Scrum Team integrate Kanban practices effectively into their existing Scrum framework