Valid SP-SAFe-Practitioner Dumps shared by ExamDiscuss.com for Helping Passing SP-SAFe-Practitioner Exam! ExamDiscuss.com now offer the newest SP-SAFe-Practitioner exam dumps, the ExamDiscuss.com SP-SAFe-Practitioner exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com SP-SAFe-Practitioner dumps with Test Engine here:
On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further. What is the PO's best course of action?
Correct Answer: B
Explanation The PO's best course of action is to communicate the status of the Iteration to all stakeholders, including the other teams on the Agile Release Train (ART), the Release Train Engineer (RTE), the System Architect/Engineer, the Product Management, and the Business Owners. This will help to align expectations, manage dependencies, and mitigate risks. The PO should also collaborate with the team and the stakeholders to prioritize the remaining work and identify the most valuable Stories to deliver by the end of the Iteration. The PO should not defer acceptance testing to the next Iteration, as this would violate the Definition of Done and compromise the quality of the system increment. The PO should not have an emergency Iteration Planning meeting, as this would disrupt the cadence and synchronization of the ART and waste time and resources. The PO should not stop the current Iteration and plan a new Iteration with the new knowledge, as this would also disrupt the cadence and synchronization of the ART and create confusion and uncertainty. References: Team Backlog - Scaled Agile Framework, Iteration Planning - Scaled Agile Framework, Iteration Execution - Scaled Agile Framework