Valid Development-Lifecycle-and-Deployment-Designer Dumps shared by ExamDiscuss.com for Helping Passing Development-Lifecycle-and-Deployment-Designer Exam! ExamDiscuss.com now offer the newest Development-Lifecycle-and-Deployment-Designer exam dumps, the ExamDiscuss.com Development-Lifecycle-and-Deployment-Designer exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com Development-Lifecycle-and-Deployment-Designer dumps with Test Engine here:
Access Development-Lifecycle-and-Deployment-Designer Dumps Premium Version
(226 Q&As Dumps, 35%OFF Special Discount Code: freecram)
Enter your email address to download Salesforce.Development-Lifecycle-and-Deployment-Designer.v2022-05-03.q106.pdf
Recent Comments (The most recent comments are at the top.)
D makes more sense. The source of truth is always the repo. C is going to cause stress and complications when merging newer developments.
I might have misunderstood in this question. But D does not mention about next sprint strategy.
D is not correct. A should be correct. What does "All fixes must be made in the release branch" means in this situation?
All fixes come from new sprint? Usually to begin next spring, new feature branch should be created from developer branch. They can start next spring in feature branch.
Moreover, if current sprint changes are not approved and need to be fixed, they must be fixed in developer branch and create release branch again and deploy to production. If release branch is not created, they could deploy from developer branch.
My selection is that D should be the correct answer
Yes D is the correct answer. C cannot be correct
no way it is C, since you don't want your source of truth to be org-based if there are alternative answers.
A and D are equivalents, basically. but D talks about managing fixes in testing and down the gitflow, so I would say D is correct.