Universal Containers wants to use 'Capacity Based' contractors to complete installations that often require crews and can take more than one day. What is true about 'Capacity Based Resources'? (Choose 2 options)
Correct Answer: B,C
Capacity-Based Scheduling is a simplified scheduling model (buckets of work) compared to the standard, granular optimization. Because it ignores specific travel times and start times, it has significant limitations. * Option B is correct:Capacity-Based Resources (contractors)cannotbe assigned Multi-Day Service Appointments. They work on a "Hours per Day" or "Jobs per Day" limit, and the system cannot span a single appointment record across multiple days for them. * Option C is correct:Theycannothandle Complex Work (dependencies like "Start Same Time" or "Follow Immediately"). Since the engine doesn't calculate their precise start time (it just ensures they haveenoughhours in the day), it cannot synchronize their work with other resources. * Option D is incorrect:You cannot create a Service Crew composed of Capacity-Based resources.