Valid C_S4EWM_2023 Dumps shared by ExamDiscuss.com for Helping Passing C_S4EWM_2023 Exam! ExamDiscuss.com now offer the newest C_S4EWM_2023 exam dumps, the ExamDiscuss.com C_S4EWM_2023 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_S4EWM_2023 dumps with Test Engine here:
Which document can be the reference for a Notification of Expected Goods Receipt? Note: There are 2 correct answers to this question.
Correct Answer: C,D
Comprehensive and Detailed In-Depth Explanation: The Notification of Expected Goods Receipt (EGR) in SAP EWM anticipates incoming stock. Option C ("Purchase Order") is correct as it's a common reference for external procurement EGRs, and option D ("Production Order") is correct for production-related EGRs, both configured in SPRO: SCM Extended Warehouse Management > Goods Receipt Process > Expected Goods Receipt. Option A (Inbound Delivery) is a downstream document, and option B (Sales Order) is outbound-related.