Valid MSP-Practitioner Dumps shared by EduDump.com for Helping Passing MSP-Practitioner Exam! EduDump.com now offer the newest MSP-Practitioner exam dumps, the EduDump.com MSP-Practitioner exam questions have been updated and answers have been corrected get the newest EduDump.com MSP-Practitioner dumps with Test Engine here:
The programme manager has produced a rough estimate of costs based on the recently completed roll-out of smart metered services to electricity and gas customers. Is this an appropriate application of the 'identify the programme' process, and why?
Correct Answer: B
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP: In the 'Identify the programme' process, the goal is to establish a high-level justification for the programme. At this early stage, detailed information is rarely available, and the investment of significant time and resources into precise budgeting is not yet warranted. However, a "rough order of magnitude" estimate is essential for the Sponsoring Group to make an informed decision about whether the programme is worth pursuing. Option B is the correct answer because the Programme Brief must contain a high-level business case. This includes an initial estimate of costs, benefits, and risks. The use of historical data (the previous electricity and gas rollout) is a common and appropriate technique for "top-down" estimation during this process. This "understanding of the cost" allows the SRO to determine if the programme aligns with the organization's financial capacity before committing to the more expensive 'Design the outcomes' and 'Plan progressive delivery' processes. While Option A is partially true in that detailed budgets aren't required yet, the reason it is appropriate is specifically to enable the initial "go/no-go" decision. Option C is incorrect because while more detail is added later, some estimation is mandatory now. Option D is a valid risk to the accuracy of the estimate, but it does not make the application of the process inappropriate; adjustments for the different utility types would simply be part of the estimation logic.