Valid PRINCE2-Practitioner Dumps shared by ExamDiscuss.com for Helping Passing PRINCE2-Practitioner Exam! ExamDiscuss.com now offer the newest PRINCE2-Practitioner exam dumps, the ExamDiscuss.com PRINCE2-Practitioner exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PRINCE2-Practitioner dumps with Test Engine here:
The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.'' In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e-learning course' whenever a part of the 'classroom-based training materials' gains accreditation''. Is this appropriate, and why?