Question 85/99

Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage.
Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (99q)
Question 1: Which of the following statements are True: 1. Quality manag...
Question 2: What is the purpose of a Product Status Account?...
Question 3: Scenario Additional Information (Exhibit) Further informatio...
Question 4: Project Scenario Calendar Project (Note: The companies and p...
Question 5: Scenario: The Ministry of Food Hygiene (MFH) has a quality m...
Question 6: Scenario A photographer from Portraits Ltd, a professional p...
Question 7: Scenario Additional Information Extract from the Communicati...
Question 8: Project Scenario - Health and Safety Training Project: ABC C...
Question 9: Project Scenario - Health and Safety Training Project: ABC C...
Question 10: Scenario A central government department, the Ministry of Fo...
Question 11: Additional Information Chief Executive Officer (CEO): He sta...
Question 12: Project Scenario - Health and Safety Training Project: ABC C...
Question 13: Project Scenario - Health and Safety Training Project: ABC C...
Question 14: Which statement is an appropriate entry for the Lessons Log?...
Question 15: Scenario Additional Information Chief Executive Officer (CEO...
Question 16: Scenario A photographer from Portraits Ltd, a professional p...
Question 17: Which of the following represents the four key characteristi...
Question 18: During which of the following activities is the Project Prod...
Question 19: When examining a project issue, which three aspects should b...
Question 20: Which of the following reports does not contain any informat...
Question 21: Scenario: The Ministry of Food Hygiene (MFH) has a quality m...
Question 22: Project Scenario - Health and Safety Training Project: ABC C...
Question 23: Scenario A central government department, the Ministry of Fo...
Question 24: After preparing the stage 3 plan, the project manager left t...
Question 25: In the PRINCE2 Quality review technique, who would most like...
Question 26: Drop down the right answer from Column 1 to column 2. (Exhib...
Question 27: Project Scenario - Health and Safety Training Project: ABC C...
Question 28: Scenario Additional Information Extract from the Communicati...
Question 29: Project Scenario - Health and Safety Training Project: ABC C...
Question 30: Project Scenario - Health and Safety Training Project: ABC C...
Question 31: Which of the following management products ARE updated as pa...
Question 32: The Calendar project was delivered as originally planned, an...
Question 33: Project Scenario - Health and Safety Training Project: ABC C...
Question 34: Scenario Additional Information Product Description (Exhibit...
Question 35: Scenario Product Summary A list of customers will be collate...
Question 36: If the Project Board are too busy to authorize all change re...
Question 37: Which management product do the Project Board use to decide ...
Question 38: Which principle is central to the quality theme and provides...
Question 39: Extract from the Project Product Description (with errors) (...
Question 40: INITIATING A PROJECT Here are three items of information rel...
Question 41: Scenario A photographer from Portraits Ltd, a professional p...
Question 42: Project Scenario - Health and Safety Training Project: ABC C...
Question 43: The project is part of a program to increase the number of A...
Question 44: Scenario: The Ministry of Food Hygiene (MFH) has a quality m...
Question 45: The 'capability to provide health and safety training' has b...
Question 46: Which statement is an appropriate entry for the Initiation S...
Question 47: If Project tolerances were threatened, who needs to be notif...
Question 48: When updating the project plan as part of Managing a stage b...
Question 49: While producing the Team Plan to deliver the agreed Work Pac...
Question 50: Scenario A photographer from Portraits Ltd, a professional p...
Question 51: Which statement is TRUE with regard to technical stages?...
Question 52: Which of the following principles describes this statement? ...
Question 53: Project Scenario - Health and Safety Training Project: ABC C...
Question 54: Which management product defines the detailed nature, purpos...
Question 55: Project Scenario - Health and Safety Training Project: ABC C...
Question 56: Scenario: Techniques, processes and procedures 1. Any threat...
Question 57: Scenario Additional Information Chief Executive Officer (CEO...
Question 58: Scenario Additional Information Product Description (Exhibit...
Question 59: There are four steps in the Risk Management procedure, what ...
Question 60: Who is responsible for committing user resources to the proj...
Question 61: Which of the following is the definition for an off-specific...
Question 62: Project Scenario - Health and Safety Training Project: ABC C...
Question 63: Scenario Extract from the Project Product Description (with ...
Question 64: The project is approaching the end of stage 4 and all work w...
Question 65: Project Scenario - Health and Safety Training Project: ABC C...
Question 66: Having completed designing the plan, in which order should t...
Question 67: The project board has asked user and supplier assurance to r...
Question 68: Scenario Additional Information Extract from the Communicati...
Question 69: The change control approach defines how products should be c...
Question 70: Who is responsible for ensuring that Communication Managemen...
Question 71: Who sets the tolerances for a work package?...
Question 72: Which of the following statements is true of the business in...
Question 73: The Team Manager has received notification that the new hard...
Question 74: While deciding on how the work of the project should be appr...
Question 75: Which statement is an appropriate entry for the project appr...
Question 76: As a result of experiences on previous projects, a change au...
Question 77: During previous projects, stakeholders became confused when ...
Question 78: While capturing previous lessons, the Project Manager discov...
Question 79: It is now late October and the project is in stage 3. The la...
Question 80: Which of the following risk responses can be used for either...
Question 81: PRINCE2 proposes 3 levels of Plan, which are they?...
Question 82: The project is using PRINCE2's recommended risk management p...
Question 83: Scenario Additional Information Chief Executive Officer (CEO...
Question 84: Scenario A photographer from Portraits Ltd, a professional p...
Question 85: Scenario A central government department, the Ministry of Fo...
Question 86: Scenario Additional Information (Exhibit) Further informatio...
Question 87: At the end of stage 2, an external consultant responsible fo...
Question 88: Extract from the Project Product Description (with errors) (...
Question 89: Scenario Extract from the Project Product Description (with ...
Question 90: Project Scenario Calendar Project (Note: The companies and p...
Question 91: Project Scenario - Health and Safety Training Project: ABC C...
Question 92: The executive has asked the project manager to plan for the ...
Question 93: Scenario Additional Information Product Description (Exhibit...
Question 94: The project is approaching the end of stage 4 and all work w...
Question 95: Scenario Product Summary A list of customers will be collate...
Question 96: Project Scenario - Health and Safety Training Project: ABC C...
Question 97: Scenario Additional Information (Exhibit) Further informatio...
Question 98: Starting Up a project is triggered by which of the following...
Question 99: Which of the following statements is False regarding the Ris...