Valid PRINCE2-Foundation Dumps shared by ExamDiscuss.com for Helping Passing PRINCE2-Foundation Exam! ExamDiscuss.com now offer the newest PRINCE2-Foundation exam dumps, the ExamDiscuss.com PRINCE2-Foundation exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PRINCE2-Foundation dumps with Test Engine here:
Access PRINCE2-Foundation Dumps Premium Version
(474 Q&As Dumps, 35%OFF Special Discount Code: freecram)
Enter your email address to download PRINCE2.PRINCE2-Foundation.v2023-04-17.q145.pdf
Recent Comments (The most recent comments are at the top.)
Correct answer is B - here is an extract from the workbook:
For a project to be following PRINCE2, as a minimum it must be possible to demonstrate that the project:
•is applying PRINCE2’s principles
•is meeting the minimum requirements set out in the PRINCE2 themes
•has project processes that satisfy the purpose and objectives of the PRINCE2 processes
•is either using PRINCE2’s recommended techniques or using alternative, equivalent techniques.